Heat & Glo LifeStyle SLR-B (COSMO) Vent Clearances and Framing, Pipe Clearances to Combustibles

Page 35

8 Vent Clearances and Framing

A. Pipe Clearances to Combustibles

WARNING! Risk of Fire! Maintain air space clearance to vent. DO NOT pack insulation or other combustibles:

Between ceiling firestops

Between wall shield firestops

Around vent system

Failure to keep insulation or other material away from vent pipe may cause over heating and fire.

Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm).

‡SLP heat shield - designed to be used on a wall 4-3/8 in. to 7-5/8 in. (111 mm to 194 mm thick).

‡,IZDOOWKLFNQHVVLVOHVVWKDQWKHH[LVWLQJKHDWVKLHOGVPXVWEHILHOGWULPPHG

,IZDOOWKLFNQHVVLVJUHDWHUWKDQLQD'93+60%ZLOOEHUHTXLUHG

B. Wall Penetration Framing

Combustible Wall Penetration

Whenever a combustible wall is penetrated, you must frame a hole for the wall shield fi restop(s). The wall shield

restop maintains minimum clearances and prevents cold air infi ltration.

The opening must be framed on all four sides using the same size framing materials as those used in the wall construction.

SLP pipe - A wall shield fi restop must be placed on each side of an interior wall. A minimum 1-1/2 in. (38 mm) overlap of attached heat shields must be maintained.

See Section 10.K. for information for regarding the in- stallation of a horizontal termination cap.

Non-Combustible Wall Penetration

3 in. (76 mm) top clearance

1 in. (25 mm) clearance around vertical sections

(SLP Pipe Shown)

 

Heat

3 in. (76 mm)

Shield

top clearance *

 

Heat

 

Shield

 

1 in. (25 mm)

Wall

clearance

Shield

bottom & sides

Firestop

 

WALL

 

If the hole being penetrated is surrounded by noncom- bustible materials such as concrete, a hole with diameter one in. greater than the pipe is acceptable.

Whenever a non-combustible wall is penetrated, the wall shield fi restop is only required on one side and no heat shield is necessary.

DO NOT PACK WITH

INSULATION OR

OTHER MATERIAL

* When using SLP pipe, minimum clearances from the vent pipe to combustible materi-

als at inside wall firestops are:Top: 2-1/2 in. (64 mm) Bottom: 1/2 in. (13 mm) Sides: 1 in. (25 mm)

Figure 8.1 Horizontal Venting Clearances To Combustible Materials

10 in.

A

10 in.

B

A*

B

48-1/16 in.

47-1/16 in.

*Shows center of vent framing hole for top venting. The center of the hole is one (1) in. (25.4 mm) above the center of the horizontal vent pipe.

Figure 8.2 Wall Penetration

Heat & Glo • SLR-B2195-900 Rev. P • 12/11

35

Image 35
Contents HOT Surfaces ModelWhat to do if you smell gas Homeowner Reference Information CongratulationsUser Guide Table of ContentsReference Materials Appliance SetupTroubleshooting FinishingLimited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Decorative Doors and Fronts Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Clear SpaceGAS Valve Lighting Instructions IPIFinal inspection by What to do if YOU Smell GASAfter Fireplace is Lit Frequently Asked QuestionsInitial Break-in Procedure Issue SolutionsRemote Control Maintenance and ServiceMaintenance Tasks-Homeowner Glass CleaningFirebox Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection VentingTypical Appliance System Getting StartedInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Selecting Appliance Location Framing and ClearancesConstructing the Appliance Chase Clearances Minimum Framing DimensionsNon-combustible Mantels Thick Wall Sheathing Mantel and Wall ProjectionsCombustible Mantels IN. Thick Wall Sheathing12 Non-Combustible Zone Vent Termination Minimum Clearances Termination LocationsMinimum Clearances for Termination Covered Alcove ApplicationsVent Information and Diagrams Top Vent Horizontal Termination Venting with 1 elbow Top Vent Horizontal Termination Venting with 2 elbows SLR-B Top Vent Horizontal Termination Venting with 3 elbowsInstalled Horizontally Exhaust restrictor Instructions Top Vent Vertical Termination No Elbows V1 = 44 ft. Max .4 mV1 Minimum Maximum V1 + V2 Minimum Top Vent Vertical Termination Venting with 2 elbowsTop Vent Vertical Termination Venting with 3 elbows V1 MIN H1 MAX V2 MIN H2 MAX V3 MIN Top Vent Vertical Termination Venting with 4 elbowsTermination Cap Flue Damper Prior to installing the gas applianceCoaxial to Colinear Venting Clearances to CombustiblesTermination CAP Inlet AIR Vent Pipe Connecting the DV-46DVA-GCL Adapter to Appliance Top VentConnecting the LINK-DV30B to the DV-46DVA-GCL adapter Floor HearthCombustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe SLP Install the Ceiling FirestopVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Top Vent Appliance PreparationProper Positioning, Leveling And Securing Of An Securing and Leveling the ApplianceAssemble Vent Sections Installing Vent Pipe SLP PipeSecure The Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof FlashingHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components 17 Venting through the wall Install Horizontal Termination CapGas Pressure Access Through the Valve AssemblyGas Information Fuel ConversionDisconnect Gas Valve Gas ConnectionElectrical Information Wiring RequirementsOptional Accessories Requirements IntelliFire Ignition System WiringElectrical Service and Repair Junction Box Installation Non-Combustible Materials Specification FinishingFraming and Finishing Instructions Finishing InstructionsNON-COMBUSTIBLE Boar D Wallboard Joint-Crack Prevention and Repair Finish and Sealing JointsFinishing Around Opening with Gypsum Wallboard PaintingMAX Measurement 14 IN. from TOP of MIN. Fireplace Opening Combustible MantelsOverlap Fit Method Tonic or Martini Decorative Front Facing MaterialHeat & Glo SLR-B 2195-900 Rev. P 12/11 Decorative Fronts Dimensions of Tonic Decorative FrontAppliance Setup Pilot Shield Air Shutter Settings Install the MeshAir Shutter Setting IntelliFire Ignition System TroubleshootingSymptom Possible Cause Corrective Action With fi xed glass assembly in place, verify that fl ame is en Reference Materials Appliance Dimension DiagramDVP-BEK2 Vent Components DiagramsDRC-RADIUS COOL-ADDCeiling Firestop SLP-45 45 ElbowSLP90- 90 Elbow Extended Heat ShieldBlack 305 mm 178 mm 15-1/2 394 mm Snorkel Support Box-BlackAdapter SLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP SLP-TRAPLINK-DV30B DVP-2SL DV-46DVA-GCL Optional Wire HarnessPVI-SLP SLP-LPCDo not Discard this Manual Contact Information