3Installing the Fireplace

Step 1. Locating the Fireplace

The diagram below shows space and clearance require- ments for locating a fireplace within a room.

A

 

B

C

D

E

42”

22”

36”

51”

72”

Figure 2.

Fireplace Dimensions, Locations,

 

 

and Space Requirements

 

Clearance Requirements

The top, back, and sides of the fireplace are defined by stand-offs. The minimum clearance to a perpendicular wall extending past the face of the fireplace is one inch (25 mm). The back of the fireplace may be recessed 21 1/2 inches (546 mm) into combustible construction.

Minimum Clearances

from the Fireplace to Combustible Materials

 

Inches

mm

Glass Front

........................ 36

914

Floor

0

0

Rear

1/2

13

Sides

1/2

13

Top

3 1/2

89

Ceiling*

31

787

*The clearance to the ceiling is measured from the top of the unit, excluding the standoffs (see Figure 35).

The distance from the unit to combustible construction is to be measured from the unit outer wrap surface to the combustible construction, NOT from the screw heads that secure the unit together.

Minimum Clearances

from the Vent Pipe to Combustible Materials

 

Inches

mm

Vertical Sections

1

25

Horizontal Sections

 

 

Top

3

75

Bottom

1

25

Sides

1

25

At Wall Firestops

 

 

Top

2 1/2

63.7

Bottom

1/2

13

Sides

1

25

For minimum clearances, see the direct vent termination clearance diagrams on pages 22 and 23 in this manual.

9

Image 9
Contents What to do if you smell gas Installers GuideSafety and Warning Information Table of Contents Service Parts LOGS-BE41 BE-41 Service Parts List / Liste des pièces de rechangeInstallation Codes High Altitude InstallationsAppliance Certification CertificationIntroducing the Heat-N-Glo Gas Fireplaces Pre-install PreparationANY Such Action MAY Possibly Cause a Fire Hazard GAS Line AccessFireplace Dimensions, Locations Locating the FireplaceSpace Requirements Clearance Requirements Framing the Fireplace Framing DimensionsAT Each Joint Vent System Approvals Installing the Vent SystemIdentifying Vent Components Terminations KitsVertical Venting MAX .4 MStraight Up Vertical Venting Venting with One 90 Elbow Venting with ONE 1 90 ElbowVenting with TWO Elbows Venting with three 90 elbows Venting with Three 3 90 Elbows+ H 1 FT Venting Out the Rear Vent Installing Vent ComponentsVenting Out the Top Vent Attach the First Vent Component to the Starting CollarsContinue Adding Vent Components Install Support Brackets12 Hole and Vent Pipe Attic Firestop Vent TerminationMinimum for vinyl clad soffits =VENT Terminal =AIR Supply InletMinimum Height from Roof to Lowest Discharge Opening Gas Control Systems Positioning, Leveling, Securing the FireplaceLeveling and Securing of a Fireplace Standing Pilot Ignition SystemGas Pressure Requirements Gas Supply LineFor Standing Pilot Ignition Wiring Appliance Requirements Wiring the FireplaceOptional Accessories Remote Wall SwitchInstalling the Trim Installing Trim, Logs, and Ember MaterialFinishing Hearth ExtensionsPositioning the Logs BeforeLog Placement Tabs Before Lighting the Fireplace After the InstallationLighting the Fireplace TemperedImportant Turn OFF the GAS Before Servicing Your Fireplace Fireplace Maintenance