BRK electronic Mx-1000 manual Introduction, Commissioning Checklist

Page 19

13 Commissioning

13.1Introduction

The following equipment should be available where possible to minimise commissioning time:

i)VHF/UHF Portable Radio (for two engineers)

ii)Multi-meter or equivalent

13.2Commissioning Checklist

1.Before commissioning, the engineer should check the following:

i)All field wiring has been inspected and tested in accordance with CEL wiring recommendations, current issues of BS5839:1 and BS7671 IEE wiring regulations.

ii)All field cables are glanded into the control panel cabinet.

iii)Detector bases are terminated but detector heads are not fitted. Any devices with electronic components are not fitted. Terminations to devices with electronic components should be linked through to maintain cable continuity.

iv)Manual Call Points are not connected but cable is linked through to maintain continuity.

v)No end-of-line devices (e.g. alarm circuit EOL resistor) are fitted in the field.

2.The following information should be available to the commissioning team:

i)Detection layout drawings.

ii)Wiring schematic diagram.

v)Control Panel installation manuals.

vi)Installation manuals for all equipment connected to the system.

vii)Site specific configuration details.

Experience has shown that tracing wiring faults on long circuits that are routed through risers etc. can be difficult without knowledge of the wiring route.

It is recommended that the electrical installer be made available until basic wiring continuity is proven. A minimum of two persons (e.g. engineer and mate) is recommended for efficient commissioning.

13.3An Overview Of The Commissioning Procedure

Commissioning is broken in to 3 sections:

i)Pre-commissioning wiring check.

ii)Powering the panel up with no field wiring connected, configuring the panel in accordance with the site-specific requirements and carrying out a functional check.

iii)Functional testing of all circuits and field devices to check each circuit and function in turn to ensure correct operation of the entire system.

In this way any faults may be located quickly and accurately. The general procedures are as follows:

Alarm circuits should be checked first. The correct operation of each sounder should be checked for correct audibility as specified in BS5839:1, using the Evacuate function.

Detection zones should be commissioned next. The purpose is to establish the correct functioning of each device and checking for correct indication at the control panel. The panel responses as configured should be checked at this time.

All ancillary inputs and outputs should be commissioned and the functionality confirmed.

Fire protection signals should be tested.

Page 19 of 40

Image 19 Contents
Technical Data Sheet List Of Contents List of Tables List Of FiguresInstall all field wiring and equipment Overview of Installation and CommissioningIntroduction Mx-1002 / Mx-1004 Internal View Internal Panel ViewsMx-1032 Internal View Page Typical Wiring Diagram Mx-1016 16 -Zone Typical Wiring Schematic2-16 Zone Motherboard Termination Details Circuit Connection Details16 Zone Expansion Board Termination Details C1627 Motherboard Layout Mx-1000 Series C1627 Motherboard FeaturesPower Supplies 10 Mx-1000 Series C1632 16-Zone Expansion Board FeaturesVisual indications 11.3 32-Zone Power Supply Features And Connections Battery DisconnectElectrical Safety InstallationElectrical Safety 12.2.1 Mx-1000 Series Panel Installation Instructions Installation Instructions Quantity Description Type Page Installation And Connection Of The C1631 Repeater Interface Repeater Connection Diagram Introduction Commissioning ChecklistAn Overview Of The Commissioning Procedure CommissioningPre-Commissioning Wiring Check Configuration Powering upCommissioning Procedure Commissioning zones Commissioning the Fire Protection control signal Commissioning the Fire and Fault Routing OutputsCommissioning the Class Change Input Commissioning ancillary outputs Commissioning ancillary inputsCommissioning repeaters User Indications showing optional clock module User Controls and IndicationsUser Controls showing optional clock module Switch Functionality Button Availability DescriptionZone or Output Configuration Engineer’s Zone/Output Configuration ProcessOperating the Engineer’s functions Page Invalid Configuration conditions Engineer’s Zone/Output Configuration Time-out WarningList of configuration DIL switches and their functions Page Delay 2/2 2/3 2/4 2/5 Duration Delay Switch SettingsRepeater Address C1631 setting for quantity of repeatersC1631 setting for repeater addresses Repeater QuantityTo Zero the Alarm Counter Optional Clock Module Configuration and SettingEnable/disable earth fault monitoring Standard Module Engineer ModeHhmmss Time Set MM flashing Hhmmss OFF Time MM flashing Link Position Selected Function Configuring the Clock ModuleC1651 Clock Module DIL switch 1 and Link 1 Settings Link DIL Switch Pole Position Selected FunctionEeprom Error Message 16.3 C1651 Clock Module PCB FeaturesClock Module Error Messages WP DIL Switch Error MessageROM Checksum Error message Eeprom 0 Error Eeprom 1 ErrorMechanical Mx-1000 Series Panel Repeater Specification Zone Mechanical, Electrical & Environmental SpecificationPowersonic Battery Mx-1000 Series Panel Repeater Specification Zone