Securing the Vent Sections

Vertical Sections

Vertical sections of pipe must be supported every 8 feet after the 25 foot maximum unsupported rise. The vent sup- port or plumber’s strap (spaced 120° apart) may be used to do this (see Figure 8.8).

Horizontal Sections

Horizontal sections of vent must be supported every 5 feet with a vent support or plumber’s strap.

B. Disassembly of Vent Sections

To disassemble any two pieces of pipe, rotate either section (see Figure 8.10), so that the seams on both pipe sections are aligned (see Figure 8.11). They can then be carefully pulled apart.

WARNING

Fire Risk. Explosion Risk. Combustion Fume Risk.

Use vent run supports per installation instructions.

Connect vent sections per installation instructions.

Maintain all clearances to combustibles.

Do NOT allow vent to sag below connection point to appliance.

Improper support may allow vent to sag or separate.

Figure 8.8 Securing Vertical Pipe Sections

Figure 8.9 Securing Horizontal Pipe Sections

Figure 8.10 Rotate Seams for Disassembly

Figure 8.11 Align and Disassemble Vent Sections

24

Heat & Glo • Escape-42DV2052-900 Rev. R • 10/08

Image 24 Contents
Model What to do if you smell gasHot glass will cause burns Congratulations Homeowner Reference InformationTable of Contents Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsInstallation to ensure maximum safety and benefit Getting StartedTools and Supplies Needed Inspect Firebox Framing and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesMantel Projections Hearth ExtensionTermination Locations Vent Termination Minimum ClearancesSee .4 for specific clearances Alcove Applications Vent Information and Diagrams Vent Table KeyMeasuring Standards Use of ElbowsVent Diagrams Top Vent Horizontal Termination One ElbowTwo Elbows H1+ H2Top Vent Horizontal Termination Three Elbows 12 ft V1 + V2 + H1 = 50 ft 15.2 m Max Top Vent Vertical Termination Three Elbows Ht MaxVent Clearances and Framing Pipe Clearances to CombustiblesWall Penetration Framing Combustible Wall PenetrationInstalling the Ceiling Firestop Installing Attic ShieldVertical Penetration Framing Removing Non-combustible Facing Mate- rial Assembly Appliance Preparation Securing and Leveling the Appliance Installing Non-combustible Facing Material Attaching Non-combustible Facing MaterialInstalling Vent Pipe Assembly of Vent SectionsAttaching Vent to the Firebox Assembly Assembling Pipe SectionsAssembling Minimum Installations MI Sections Assembling DVP-12A Slip SectionsDisassembly of Vent Sections Securing the Vent Sections Vertical SectionsHorizontal Sections Installing Heat Shield and Horizontal Termination Cap Installing the Horizontal Termination CapHeat Shield Requirements for Horizontal Termination Installing Roof Flashing and Vertical Termination Cap flue of the pipe see FigureAssembling and Installing Storm Collar 17 Assembling the Storm Collar Around the PipeGas Information Fuel Conversions Gas ConnectionGas Pressures Pressure Natural Gas PropaneHigh Altitude Installations Recommendation for Wire Intellifire Ignition System WiringConnecting to the Appliance Optional Accessories RequirementsDetail a PVK-80 Motor Neutral Vacuum Switch 120VAC HOT Finishing Facing MaterialFinishing Materials Requirements Non-combustible Finishing Material RequirementsAppliance Setup Clean the ApplianceAccessories Ember PlacementPositioning the Logs StepLOG #1 SRV750-706 Three LOG #2 SRV569-705 TwoLOG #3 SRV2052-701 LOG #4 SRV2012-162LOG #5 SRV2012-163 LOG #6 SRV2052-702 LOG #7 SRV2012-165LOG #8 SRV2012-166 Final StepGlass Assembly Air Shutter SettingRemoving Glass Assembly Replacing Glass AssemblyOperating Instructions Before Lighting ApplianceTurn off all electric power to the appliance On position. The ON/OFF switch mayLighting Appliance IPI Ignition Final inspection byFrequently Asked Questions Initial Break-in ProcedureAfter Appliance is Lit Troubleshooting Intellifire Ignition SystemSympton Possible Cause Corrective Action Symptom Possible Cause Corrective Action Maintenance Tasks Maintaining and Servicing ApplianceInspect Maintenance Tasks Doors, SurroundsAppliance Dimension Diagram Reference MaterialsLocation Inches Millimeters Vent Components Diagrams DVP vent componentsDVP-TRAP RF6M RF12M Log Set Assembly Service PartsPart number list on following Service Parts List StockedAt Depot IPI Valve Assembly StockedCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Contact Information