Vermont Casting DVRSL, DVRS3, DVRSR installation instructions Vertical Through Roof Applications

Page 15

FOUNDATION

RECESS

WATERTIGHT

SEAL

AROUND

PIPE

SNORKEL

WALL

SCREWS

SHEET METAL

Fig. 26

SCREWS

e)The maximum number of elbow degrees in system is 270º (this does not include transition elbow from rear vent to vertical vent).

If the foundation is recessed, use recess brackets (not supplied) for securing lower portion of the snorkel. Fasten brackets to wall first and then secure to snorkel with self drilling #8 x 1/2 sheet metal screws. It will be necessary to extend vent pipes out as far protruding wall face (Fig. 26).

VERTICAL THROUGH THE

ROOF APPLICATIONS

MAXIMUM

10 FT. (3408mm)

MINIMUM 8 FT.

MAXIMUM 40 FT.

VERTICAL RISE

PIPE STRAPS

EVERY 3 FT. (914mm)

Fig. 27

This Gas Fireplace has been approved for,

a)Vertical installations up to 40 feet (12 metres) in height. Up to a 10 ft.(3048mm) horizontal vent run can be installed within the vent system using a maximum of three 90º elbows.

b)Up to two 45º elbows may be used within the horizontal run. For each 45º elbow used on the horizontal level the maximum horizontal length must be reduced by 18 inches (457mm).

Example: Maximum horizontal length

0

-

45º elbows

10 ft. (3048mm)

1

-

45º elbows

8.5 ft. (2590mm)

2

-

45º elbows

7 ft. (2133mm)

c)A minimum of an 8 ft. vertical rise.

d)Two sets of 45 degree elbow offsets within these vertical installations. From 0 to a maximum of 8 ft. (2438mm) a vent pipe can be used between elbows. (Fig. 30)

 

 

 

 

Fig. 28

 

 

 

 

 

Sample:

1

-

90º

 

 

2

-

45º

 

 

3

-

45º

 

 

4

-

45º

 

 

5

-

90º

 

 

 

 

 

 

 

Total

-

270º

 

f)7DVCS must be used to support offsets. (Fig. 30). This application will require that you first determine the roof pitch and use the appropriate 7DVSKV (A,B or F). (see Venting Components, page 17)

- 15 -

Image 15 Contents
DVRS3 Dvrsl Dvrsr Table of Contents Locating Your Majestic GAS Fireplace Installation and Operating InstructionsFireplace Dimensions Mantel ChartMantels Final Finishing GAS SpecificationsClearance to Combustibles Framing and FinishingRemote Switch Installation GAS Line InstallationGeneral Venting Termination Clearances Rear Venting Applications Rear Wall InstallationsMaximum Vertical Sidewall Applications 120 HOW to USE the Vent Graph Vertical Sidewall InstallationVertical Sidewall Venting Graph SCREWS2 Installation Below Grade InstallationsVertical Through Roof Applications Vertical Thru the Roof Installation DVR Series Crimped Venting Components General Information on Assembling Twist Lock Vent Pipes Vent Opening Combustible Wall Vertical Sidewall Installations Sidewall Venting Graph Vent Sidewall Installation Zero Clearance Sleeve if Required Firestop Two sets of 45 degree elbow offsets within these Vertical Through the Roof Installation DVR Series Twist Lock Venting Components Side Glass Removal Louvre Removal Front Glass RemovalCeramic Refractory Installation Glass CleaningInstallation of Logs Ember Material PlacementLava Rock To Turn OFF GAS to Fireplace Lighting InstructionsSIT 820 Nova Millivolt Valve Trouble Shooting the GAS Control SystemCleaning the Standing Pilot Control System Flame AdjustmentFlame Characteristics MaintenanceReplacement Parts DVRS3 & Dvrsl / Dvrsr Description Replacement Parts List DVRS3/DVRSL/DVRSRRemote Control OptionsFAN KIT FK24