7-INSTALLATION (continued)

7-INSTALLATION (continued)

7.5 Removal of Plastic TIes

Cut the plastic which attaches the top head to the frame and remove the polystyrene blocks (Figure 7-4).

Figure 7-4

Cut the plastic ties holding the lower taping head in position (Figure 7-6).

Figure 7-6

Cut the plastic strap which attaches the strip and the

EMERGENCY STOP cable to the frame (Figure 7-5).

7.6 Assembly Completion

1 Crank - Install the crank handle on the top of the left column as shown (Figure 7-7B).

Upper taping head frame height adjustment crank is installed on top of the left column. If desired, for operator convenience, it may be moved to the right side of the machine.

2 Tape Drum Bracket - Install the upper tape drum bracket on the top cross bar as shown

(Figure 7-7A).

Figure 7-5

Upper Tape

Drum Bracket

Fig. 7-7A

Crank

Assembly

Fig. 7-7B

 

Figure 7-7

 

700aks-NA

 

2011 October

 

19

Page 31