30.Attach the control assembly's support tube to the welded bracket below the discharge chute using (2) 5/16" x 1-1/4" carriage bolts and (2) 5/16" nylock nuts. Do not tighten yet.

31.Tighten bolts assembled in steps 29 and 30.

SECURE CABLES HERE

NYLON TIE

CHUTE TILT CONTROL

BOWED

WASHER

5/16" x 1-3/4"

CARRIAGE BOLT

5/16" NYLOCK

NUT

5/16" NYLOCK NUTS

5/16" x 1-1/4"

CARRIAGE BOLTS

 

 

figure 23

figure25

38.Insert the wire harness into the large hole at the front of the control box.

39.Connect the wire harness to the switch.

40.Using nylon ties, secure the wire harness and clutch cable to the handle assembly to keep them from interfering with moving parts.

32. Cut the nylon tie that holds the two chute crank brackets together.

33. Attach the chute crank brackets to the discharge housing using (2) 5/16" x 1" carriage bolts, 5/16" washers and 5/16" nylock nuts. Do not tighten yet.

34. Adjust position of chute crank brackets so that spiral does not rub bottom of discharge chute notches.

35. Tighten bolts and nuts assembled in step 33.

NOTE: Spiral not shown for clarity.

figure 26

 

5/16" x 1"

 

CARRIAGE BOLT

41. Roll the ATV up behind the snow thrower, keeping the

 

 

push channel centered between the stabilizer brackets.

 

Make sure the guide bracket will slide in between

 

the stabilizer brackets as shown in figure 27. Keep a

 

minimum clearance of 3"-4" between the front of the

 

ATV and the snow thrower.

5/16" WASHER

NOTE: ATV not shown below for clarity.

5/16" NYLOCK

STABILIZER BRACKETS

NUT

 

 

GUIDE BRACKET

figure 24

 

36. Attach the chute tilt control to the control assembly

 

using (2) 5/16" x 1-3/4" carriage bolts, (2) bowed

 

washers and (2) 5/16" nylock nuts.

 

37. Using a nylon tie, secure the cables from the chute tilt

 

control to the support tube as shown in figure 25.

 

Note: Do not secure the chute tilt control cables in locations

figure 27

other than the one shown.

11