Concrete Foundation Pad

Installation

A concrete foundation and pad may be constructed to elevate the machines. Care must be exercised in the design of the foundation pad due to the force exerted by the machine during extract. This concrete base (recommended not to exceed 8 inches [20.32 cm]) must be poured, reinforced with rebar and tied to the existing 12 inch (30.48 cm) minimum floor. Refer to Figure 5 and Table 2.

IMPORTANT: Do NOT install a pad on top of the existing floor. The foundation and pad must be constructed and tied together as one piece.

If the existing floor is not reinforced concrete at least

12inches (305 mm) thick over a solid foundation, the following steps must be performed (refer to Figure 5):

1.Cut a hole larger on all sides than the machine base through the existing floor. The foundation should extend a minimum of 9 inches (229 mm) for UW35 models or 12 inches (305 mm) for UW60 - 150 models out from the machine on all sides.

2.Excavate to a depth of 18 inches (457 mm) from the top of the existing floor.

3.Produce a PYRAMID-SHAPEDhole by excavating the bottom of the hole to a width 6 inches wider on each side than the width of the top of the hole.

4.If installing a foundation and pad, prepare a form for the above-ground portion of the foundation. Verify that the top of the foundation is level. The height of the foundation pad must not exceed 8 inches (203 mm) above the existing floor.

Specifications and Dimensions

5.Refill with compacted fill dirt, making sure to allow for correct concrete thickness.

6.Wet the hole around the cement foundation well and brush the exposed foundation with cement grout.

7.Completely fill with a minimum of 12 inches (305 mm) up to the existing foundation level plus any added level for the desired elevated pad. The concrete must be poured so that the entire foundation and pad cures as one piece.

8.For new foundations only a bolt-locator fixture or a rebar frame is available and a preferred option. Embed the mounting bolts or rebar frame as the concrete is poured. Ensure that the bolt threads extend 2 inches (51 mm) for UW35 - 125 models and 3 inches (76 mm) for UW150 models above floor level.

9.Allow concrete to dry.

10.Proceed to Machine Mounting and Grouting section.

NOTE: If the washer-extractor installation will include the Premium Wet Clean Module, the elevated base must be designed to accommodate the additional depth of 24 inches (60.96 cm).

For technical assistance, contact your local distributor or call Alliance Laundry Systems at (920) 748-3121.

F232084

© Copyright, Alliance Laundry Systems LLC – DO NOT COPY or TRANSMIT

15