Route the input conductors to the

Main Input circuit breaker (or switch) . . . . . . . . . . . . . . . . . 16

Torque specs and tools required . . . . . . . . . . . . . . . . . . . . 16

Connect input conductors . . . . . . . . . . . . . . . . . . . . . . . . 17

Connect an Emergency Power Off Switch . . . . . . . . . . . . . . . . 18

Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

Connect an EPO switch to the

user connection plate and test the switch . . . . . . . . . . . . . . 18 Safety warnings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

Connect User Input Contacts and

Relay Outputs to the User Connection Plate. . . . . . . . . . . . . . . 21

Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

How to connect contacts to the PDU Monitoring Unit . . . . . . 22

Install Shielding Troughs,

Shielding Partitions, and Cable Ladders . . . . . . . . . . . . . . . . . . 23

Shielding Troughs and Shielding Partitions for

overhead wiring along rows . . . . . . . . . . . . . . . . . . . . . . . 23 Cable Ladders for overhead wiring across rows . . . . . . . . . . 24

Install InfraStruXure Rack-Mount Devices . . . . . . . . . . . . . . . . . 25

Install the Rack Automatic Transfer Switches (ATS) . . .

. . . . . 25

Install the Rack Power Distribution Units (PDU)

. . . . . 25

Install the InfraStruXure Manager and Hub (or Switch)

. . . . . 25

Install the Environmental Monitoring Unit or

 

Environmental Management System

. . . . . 25

Route and Attach Overhead Wiring

. . . . . . . . . . . . 26

Wiring Under the Floor

. . . . . . . . . . . . 29

Route Data Cables to the

 

InfraStruXure Manager Hub (or Switch)

. . . . . . . . . . . . 31

Start-Up Procedure

33

Safety warnings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33

Ensure that all power is off . . . . . . . . . . . . . . . . . . . . . . . . 33

Apply power to the system . . . . . . . . . . . . . . . . . . . . . . . . 34

Configure the InfraStruXure Manager. . . . . . . . . . . . . . . . . . . . 36

iv

InfraStruXure System—Installation and Start-Up

Page 6
Image 6
American Power Conversion 60kW InfraStruXureTM System manual Start-Up Procedure

60kW InfraStruXureTM System specifications

The American Power Conversion (APC) 60kW InfraStruXure™ System represents a groundbreaking advancement in power management for critical facilities. Designed for data centers and environments with extensive IT infrastructure, this system stands out for its scalability, reliability, and efficiency.

One of the primary features of the InfraStruXure™ System is its modular architecture. This design allows for the deployment of power and cooling components in a customized manner, tailored to the specific needs of each facility. The system can grow alongside business needs, accommodating increased power demands simply by adding additional capacity modules. This flexibility means that organizations can adapt without the often hefty costs and complexities associated with traditional infrastructure upgrades.

The 60kW configuration supports a range of power distribution options, ensuring that it can serve diverse loads while maintaining optimal performance. The system includes integrated power distribution units, which facilitate seamless integration with existing setups. This integration is crucial for organizations wishing to enhance their infrastructure without undergoing extensive overhauls.

Moreover, the InfraStruXure™ System leverages advanced cooling technologies to maintain operational efficiency. Its intelligent cooling systems optimize airflow management, helping to prevent hotspots and maintain an even thermal profile throughout the data center. The cooling units are designed to work in conjunction with the power modules, ensuring that the entire system operates with minimal energy wastage.

In terms of monitoring and management, the InfraStruXure™ System is equipped with an intuitive interface that provides real-time visibility into system performance. This includes alerts and status updates that enable quick responses to potential issues, ensuring high levels of uptime. The integration of remote monitoring capabilities allows facility managers to keep an eye on performance from anywhere, further enhancing operational management.

Reliability is another cornerstone of the InfraStruXure™ System. Built-in redundancy features minimize the risk of downtime, while the rugged reliability of APC products ensures long-term performance. Power quality management features protect sensitive equipment from surges and disruptions, critical in environments where every second of uptime counts.

In conclusion, the APC 60kW InfraStruXure™ System is a state-of-the-art solution designed to meet the evolving demands of modern data centers. With its modular design, robust power distribution, intelligent cooling, and advanced monitoring capabilities, it offers organizations an efficient, reliable, and scalable power management solution that stands up to the challenges of today’s technology-driven world.