Electrical Installation: Bypass Static Switch Wiring

Bottom cable entry

Top view of bottom cable entry

UPS Summary

 

~

~

Top view of AC IN & OUT bottom cable connections

L1 IN

L1 OUT

L2 IN

L2 OUT

L3 IN

L3 OUT

Communication cable Port

L1 IN

L1 OUT

L2 IN

L2 OUT

L3 IN

L3 OUT

PE

 

1.75 in /

1.75 in /

44.45 mm

44.45 mm

 

 

2.3 in / 58 mm

Loosen the 8 bolts to remove bottom cover.

No drilling or cutting should take place inside the UPS.

Note

Drill holes for conduits. Re-fit the covers. Install the conduits.

Feed cables through conduits. Connect cables at cable connection points as illustrated.

Connect grounding electrode conductor to busbar locations as shown.

20

Symmetra MW 1000 kW 480 V Installation - 990-4112E

Page 24
Image 24
American Power Conversion MW manual Bottom cable entry