American Power Conversion RT XLI/XLICH user manual Stack configuration, Rack-mount configuration

Models: RT XLI/XLICH

1 34
Download 34 pages 44.93 Kb
Page 8
Image 8

Stack configuration

The UPS and the XLBBP(s) must be connected with ground wires. Refer to the XLBP user manual for details.

Always place the UPS above the XLBP(s) in a stack configuration.

Total stack configuration height is recommended NOT to exceed 18U. This is the equivalent of two XLBPs and one UPS.

Four screws must be used to secure each tie bracket to the units, (see diagram).

For detailed instructions on installing batteries, the battery doors, refer to the Rack-mount configuration section of this manual.

Refer to the Rack-mount configuration section in this manual for cable routing and bezel installation details.

8x

Tie Brackets (included with XLBP)

Rack-mount configuration

Install rack-mount brackets

Four flat head screws must be used to secure each rack-mount bracket to the unit.

4x

Install rail cleats

Two pan head screws must be used to secure each rail cleat to the unit.

2x

Install rails in rack.

For details on rail installation refer to the instructions included in the rail kit package.

Mount units in rack

The UPS and XLBP should be installed at or near the bottom of the rack. Always place the UPS above the XLBP(s). Batteries must be removed from the XLBP(s) prior to installing the unit(s) in a rack. Refer to the instructions on the packaging for details on removing the batteries from the XLBP.

4

Smart-UPS RT 15000/20000 VA 230 Vac Stack/Rack-Mount 6U User Manual