OPERATION AND SERVICE
OPERATION AND SERVICE
SEQUENCE OF OPERATION
1.Call for heat is activated when temperature sensed from Thermistor Probes falls below the Thermostat setting.
2.Blower (Draft Inducer) is energized.
3.Ignition Control Board verifies that the Blower Prover Switch is closed and that the Blower (Draft Inducer) is operating.
4.Igniter is energized.
5.Gas Valve is energized and burners ignite
6.Ignition Control Board verifies flame at burners.
7.Water is heated to Thermostat set point.
8.Gas Valve is
9.Blower runs for purge period and is
10.Ignition Control Board goes into standby mode and Blower Prover Switch Opens.
Blower (Draft Inducer)
Thermistors
(probes)
Main Gas
Valve
Main | Hot Surface Igniter |
Burner | (Not Shown) |
Figure 9
Servicing should only be performed by a Qualified Service Agent