Section 2. ET Tower Installation

DANGER: Do not install near power lines. If any part of the tower comes in contact with power lines you could be KILLED. Contact local utilities for the location of buried utility lines before digging or driving grounding rods.

CAUTION: Do not fit the 3 meter ET Tower sections together until the appropriate time. Once attached, they cannot be detached.

The ET Tower provides a support structure for mounting the ET101 and ET106 weather station components. Figure 2.1-1 shows a typical ET Tower installation option. The tower is designed to withstand winds of 100 mph. The lightning rod assembly is attached after the instrumentation enclosure is installed (Section 3.1).

Transformer

User Supplied

Junction Box

ET Tower

16 VAC Power

110 VAC

Valve Box

Ground

Rod

Communications

Direct Bury

Concrete

Line

Splices

Base

FIGURE 2.1-1. ET Tower Installation

2.1Base Installation

2.1.1Supplied Components

(3)½ inch L-Bolts

(9)½ inch Nuts

(1)Anchor Template

Refer to Section 1 for components supplied by installer.

2-1