SIDE VIEW

Section 2. ET Tower Installation

FORM

TOP VIEW

2"

FORM WIRE

NORTH

 

 

ANCHOR BOLT

24"

SMALL

24"

 

 

 

CAVITY

 

 

 

CEMENT PAD

24"

FORM WIRE

TEMPLATE

FIGURE 2.1-2. ET Tower Base Installation

2.2Tower Installation

2.2.1Supplied Components

(1)Upper Tower Section (Tapered)

(1)Lower Tower Section

(6)½ inch Washers

(1)12 foot 12 AWG Ground Cable

(1)Tower Cap

(1)20' communications cable

(1)20' power cable

Refer to Section 1 for components supplied by installer.

2.2.2 Installation

Attach the tower to the base as shown in Figure 2.2-1.

1.Dig a hole close to the concrete base to access the lower conduit opening. From the hole, trench to the power and communications sources. Remove the duct tape from both ends of the conduit.

2.Remove the template. Attach the two pieces of the tower. This is a permanent connection and cannot be undone. Lay the tower on the ground with the base next to the concrete foundation.

3.Thread communications and power cables through the tower and conduit. Electrical fish tape will help.

2-3