B. Preliminary Equipment Check (YES or NO) (cont)
HAVE POWER SIDE ELECTRICAL COMPONENT CONNECTIONS BEEN CHECKED FOR TIGHTNESS? ON 30HK,HL UNITS, IS THE PROPER CONTROL VOLTAGE SUPPLIED TO
ON 30HK,HL 50 HZ UNITS, IS THE BLACK WIRE GOING TO TRAN1 AND TRAN2 CONNECTED TO THE RED LEAD FROM THE TRANSFORMER?
CHECK AIR SYSTEMS (YES OR NO)
ARE ALL AIR HANDLERS OPERATING? (refer to
ARE ALL CHILLED FLUID VALVES OPEN?
IS THE FLUID PIPING CONNECTED PROPERLY? |
| |
HAS ALL AIR BEEN VENTED FROM THE COOLER LOOP? |
| |
IS THE CHILLED WATER (FLUID) PUMP (CWP) OPERATING? |
| |
IS THE CWP ROTATION CORRECT? |
|
|
CWP MOTOR AMPERAGE: | Rated | Actual |
C.Unit
HAS THE CHILLER BEEN PROPERLY INTERLOCKED WITH THE AUXILIARY CONTACTS OF THE CONDENSER WATER PUMP STARTER?
ASSURE THAT UNIT IS SUPPLIED WITH CORRECT CONTROL VOLTAGE POWER.
ASSURE CRANKCASE HEATERS HAVE BEEN ENERGIZED FOR A MINIMUM OF 24 HOURS PRIOR TO
ASSURE COMPRESSOR OIL LEVEL IS CORRECT.
ASSURE LIQUID LINE SERVICE VALVE(S) IS BACKSEATED.
ASSURE COMPRESSOR DISCHARGE SERVICE VALVE(S) IS BACKSEATED. ASSURE COMPRESSOR SUCTION SERVICE VALVE(S) IS BACKSEATED. LOOSEN COMPRESSOR SHIPPING ISOLATOR LOCKNUTS.
OPEN GAGE PANEL SERVICE VALVES.
BE SURE TEMPERATURE CONTROLLER DEADBAND AND SAMPLE RATE SETTINGS ARE SET.
SET POINT SHOULD BE ADJUSTED TO THE DESIRED COOLER LEAVING FLUID TEMPERATURE. (refer to installation instructions)
LEAK CHECK THOROUGHLY: COMPRESSOR(S), CONDENSER FITTINGS, TXV(s), SOLENOID VALVE(S), FILTER DRIER(S), FUSIBLE PLUG(S), AND COOLER HEAD(S), WITH GENERAL ELECTRIC
LOCATE, REPAIR, AND REPORT ANY
CHECK VOLTAGE IMBALANCE: | AB |
|
|
| AC |
|
| BC |
|
| |||||
AB + AC + BC (divided by 3) = AVERAGE VOLTAGE = |
|
|
|
|
|
| V | ||||||||
MAXIMUM DEVIATION FROM AVERAGE VOLTAGE | = |
|
|
|
|
|
|
|
|
| |||||
| (MAX. DEVIATION) |
|
|
|
|
|
|
|
|
|
|
| |||
VOLTAGE IMBALANCE = |
| x 100 = |
|
|
|
|
|
| % VOLTAGE IMBALANCE | ||||||
AVERAGE VOLTAGE |
|
|
|
| |||||||||||
|
|
|
|
|
|
IF OVER 2% VOLTAGE IMBALANCE, DO NOT ATTEMPT TO START CHILLER!
CALL LOCAL POWER COMPANY FOR ASSISTANCE.
ASSURE THAT INCOMING POWER VOLTAGE TO CHILLER IS WITHIN RATED UNIT VOLTAGE RANGE.
SYSTEM FLUID VOLUME IN LOOP: TYPE SYSTEM: |
|
|
| |
AIR CONDITIONING Ð MINIMUM 3 GAL. (3.25 L) PER NOMINAL TON (kW) = |
|
| GAL. (L) | |
PROCESS COOLING Ð MINIMUM 6 GAL. (6.5 L) PER NOMINAL TON (kW) = |
|
| GAL. (L) |