Models
Gas-Fired Natural Draft Water Boilers INSTALLATION INSTRUCTIONS
CWI Series
These instructions must be affixed on or adjacent to the boiler
Table of Contents
I Product Description
FIGURE 1 CWI BOILERS - GENERALCONFIGURATION
II Specifications
TABLE 1 CWI SPECIFICATIONS
III Before Installing
IV Locating the Boiler
V Air for Combustion and Ventilation
ForBuildingsofUnusuallyTightConstruction
For Buildings of Other than Unusually Tight Construction
Example
FIGURE 4 ALL AIR FROM OUTDOORS, VENTILATED CRAWL SPACE AND ATTIC
FIGURE3BOILERINSTALLEDINCONFINEDSPACE, ALL AIR FROM INSIDE
FIGURE 5 ALL AIR FROM OUTDOORS VIA VENTILATED ATTIC
FIGURE 6 ALL AIR FROM OUTDOORS, USING OPENINGS INTO BOILER ROOM
VI Venting
Removing an Existing Boiler from a Common Chimney
FIGURE8 CWI BOILERTYPICALVENTSYSTEM INSTALLATION AND COMPONENTS
FIGURE 9 VENT DAMPER INSTALLATION DETAILS
VII Gas Piping
StandardPiping
VIII System Piping
DANGER
1413
Piping for Special Situations
FIGURE 11 STANDARD BOILER PIPING FIGURE 12 INDIRECT WATER HEATER
BOILERSIDEPIPING
FIGURE13 BOILERBYPASSPIPING
FIGURE14 ISOLATIONOFBOILERFROMSYSTEMWITHAHEATEXCHANGER
FIGURE15 BOILERPIPINGWITHCHILLER
IX TANKLESS HEATER PIPING
Feel water before showering or bathing
A mixing valve does not eliminate the risk of scalding
FIGURE 17TANKLESSHEATERPIPING
IX Wiring
SingleZoneWiring
FIGURE 20 WIRING DIAGRAM, STANDING PILOT WITH TANKLESS HEATER
Wiring Variations
FIGURE23ZONEWIRINGUSINGHONEYWELLV8043FZONEVALVES
FIGURE 22 CIRCULATOR ZONEWIRING USING HONEYWELLR845As
FACTORY BOILER WIRING NOT SHOWN - SEE FIGURES 18
FACTORYWIRING NOT SHOWN - SEE FIGURES 18
Sequence of Operation, Standing Pilot, Less Tankless Heater
CWI Control System - Sequence of Operation
Sequence of Operation, Standing Pilot, With Tankless Heater
Sequence of Operation, Intermittent Ignition, Less Tankless Heater
Sequence of Operation, Intermittent Ignition, With Tankless Heater
XI Start-up and Checkout
Safety Control Operation - Standing Pilot and Intermittent Ignition
2726
FIGURE 24 STANDING PILOT BURNER FLAME
Page
Page
TO TURN OFF GAS TO APPLIANCE
FOR YOUR SAFETY READ BEFORE OPERATING
LIGHTING INSTRUCTIONS
LIGHTING INSTRUCTIONS FOR BOILERS EQUIPPED WITH HONEYWELL
LIGHTING INSTRUCTIONS FOR BOILERS EQUIPPED WITH ROBERTSHAW
FOR YOUR SAFETY READ BEFORE LIGHTING
7000ERHC SERIES GAS VALVES STANDING PILOT
TO TURN OFF GAS TO APPLIANCE
FOR YOUR SAFETY READ BEFORE LIGHTING
OPERATING INSTRUCTIONS
VR8204 AND VR8304 SERIES GAS VALVES INTERMITTENT PILOT
7000DERHC SERIES GAS VALVES INTERMITTENT PILOT
FIGURE 27a GASVALVEDETAIL-HONEYWELLVR8200ORVR8300STANDINGPILOT
FIGURE 28b GASVALVEDETAIL-ROBERTSHAW 7000DERHC INTERMITTENT IGNITION
XI Service and Maintenance
Heat Exchanger Cleaning Procedure
XIII Troubleshooting
START
C1&C2?
5&6 on
National Fuel Gas Code
START
L2 ?
T&TV?
C1&C2?
C2 and
Standing Pilot Ignition System Troubleshooting Chart
Caution Read page 36 before attempting to use this chart
Intermittent Ignition System Troubleshooting Chart
XIV PARTS
Page
1/4 Pilot Tubing Used with Robertshaw Valves
These Valves Piped in Series to Provide Redundent Shut-off
40mm BURNERS ONLY
Page
KEY #
Page
B. BaseAssembly Preparation
Appendix A Knockdown Boiler Assembly Instructions
A. Before Installing
C. Heat Exchanger and Flue Collector Installation
FIGUREA1 BASE, HEAT EXCHANGER, FLUE COLLECTORASSEMBLY
D. Gas Valve Installation
E. Control and Trim Installation
FIGURE A2 JACKET INSTALLATION
F. Electrical Wiring Connections
G. Complete Installation
FIGURE A3 TAPPING LOCATIONS SEE TEXT FOR TAPPING USES
3633 I. Street
P.O. Box
Philadelphia