10. The

Installation

10. The

pipe

must

 

 

extend

at

least

 

 

12”

(30

cm) away

 

 

from

the

building.

 

 

If necessary, bring

 

Exhaust Tube

another

length

of

 

 

 

pipe

(PL

type)

to

 

3" (75mm) or 4" (100mm)

the

outside

of

the

 

"PL" or "L" vent

 

Wall Thimble

home to connect to

 

 

 

the first section. Do

 

 

not forget

to place

 

 

high

temperature

 

 

silicone

around

the

 

45° Elbow with screen

pipe

that

 

passes

 

or Termination Cap

 

 

 

through

 

 

 

the

 

 

thimble.

 

 

 

 

 

 

11. Install

a

 

vertical

Fresh Air Intake

High Temperature RTV

pipe, or

 

if

all

 

 

Silicone Required

requirements

for

 

 

 

direct

 

 

venting

Figure 23: Straight through wall Installation.

are

met,

 

install

vent termination. The stainless steel cap termination manufactured by the vent manufacturer is recommended. However, when the vent terminates several feet above ground level and there are no trees, plants, etc. within several feet, a 45° elbow can be used as termination. The elbow must be turned down to prevent rain from entering.

NOTE:

Some horizontal through wall installations may require a “T” and 3 to 5 feet (91 to 152 cm) of vertical pipe outside the building to help naturally draft in the unit.

This may be required if a proper burn cannot be maintained, after the stove has been tested and the airflow set.

This is due to the back pressure in the exhaust caused by airflow around the structure.

All sections of pipe must have three (3) screws evenly spaced and all horizontal and vertical vent sections located within the house must have a bead of high temperature silicone installed on the male end of the pipe before installation to create a gas tight seal.

The termination must be 12 inches (30 cm) from the outside wall and 12 inches (30 cm) above the ground.

A 45° elbow with a rodent screen may be used in place of the termination cap (or stainless steel termination hood).

Wall framing

Horizontal frame

for thimble

Vent pipe

Termination

cap

Wall thimble

ENVIRO Meridian

Figure 24: Straight through Wall Installation - Side View.

19

Page 19
Image 19
Enviro Meridian owner manual Installation, The

FAQ

What is the recommended termination cap for the vent?

The stainless steel cap termination manufactured by the vent manufacturer is recommended. However, a 45 elbow with a rodent screen may also be used.

What should be used to create a gas tight seal on the vent sections?

All sections of pipe must have three screws evenly spaced and a bead of high temperature silicone installed on the male end of the pipe before installation to create a gas tight seal.

How far should the termination be from the outside wall?

The termination must be 12 inches (30 cm) from the outside wall and 12 inches (30 cm) above the ground.