1. Create and Register Each Resource
Create and register each resource.
Perform resource creation and registration, referring to "Chapter 5 Registering Resources" and "Chapter 14 Registering Resources
in Resource Pools".
2. Create an L-Server
Create an L-Server for which only the configuration definition (defined) is created, referring to "Chapter 16 Creating L-Servers".
Perform the following configuration:
-Set [Deploy] for image deployment from the select a cloning image section of the [General] tab.
-Check the [None (Definition only)] checkbox on the [General] tab.
-Check the [Automatic (when powered off)] checkbox of [Resource release] on the [Server] tab.
Operation
The operation method is shown below.
-When using multiple L-Servers, switching between them, on a single physical server
Usage can be changed by repeating the following procedure.
1. Check the Physical Server and L-Server of the Source L-Server for Usage Change
2. Stop the Source L-Server for Usage Change
Stop L-Servers operating on physical servers which are required for change usage.
For details, refer to "17.1.2 Stopping an L-Server".
3. Start the Destination L-Server for Usage Change
For details, refer to "17.1.1 Starting an L-Server".
After changing the configuration, the L-Server before changing cannot be operated, until the new L-Server has finished starting.
-When using multiple L-Servers, switching between them, on unused physical servers in a server pool
Usage can be changed by repeating the following procedure.
1. Confirm the Server Pool
Confirm whether an unused physical server exists in the server pool.
2. Start the Destination L-Server for Usage Change
For details, refer to "17.1.1 Starting an L-Server".
After changing the configuration, the L-Server before changing cannot be operated, until the new L-Server has finished starting.
17.9.1.2 When Resources are Already Allocated (allocated)
This section explains configuration and operation when resources have been allocated to the L-Server.
Settings
Perform step 1 the same number of times as the number of physical servers which are used for usage change.
1. Create and Register Each Resource
Perform resource creation and registration, referring to "Chapter 5 Registering Resources" and "Chapter 14 Registering Resources
in Resource Pools".
- 224 -