Installation Procedure
Be sure to arrange the drain hose correctly so that it is leveled lower than the drain hose connecting port of the indoor unit. (Fig.7)
Fig.7 | OK | NO | NO |
Arrange the drain hose | Drain hose |
lower than this portion. |
|
CAUTION:
Do not install the unit drain hose side is too high. Height A should be less than 5 mm.(Fig.8)
B. UNDER CEILING TYPE
Using the installation template, drill holes for piping and anchor bolts(for holes).(Fig.9)
Fig.8 |
|
Drain hose | |
A | A |
Fig.9 |
|
900m |
|
|
| Drilling position | |
200m | Installation | for anchor bolt | |
| |||
template | Ceilling | ||
| |||
|
| ||
|
| Wall | |
| Drilling position |
| |
| for piping |
|
1.Drilling for piping
Select piping and drain directions. (Fig.10)
CAUTION:
Install the drain hose at the rear. It should not be installed on the top or right side.
Fig. 10 | Rear (Install the drain |
| |
| hose in the direction.) |
| Right |
When the directions are selected, drill 80mm and 50mm | Fig.11 |
or 150mm dia. hole on the wall so that the hole is tilted |
|
downward toward the outdoor for smooth water flow. |
|
(Fig.11) |
|
|
|
2.Drilling holes for anchor bolts and installing the |
| Fig.12 |
anchor bolts |
|
|
With a concrete drill, drill four 12.7 mm dia. Holes. |
|
|
(Fig.12) |
|
|
Insert the anchor bolts into the drilled holes, and drive |
| Fig.13 |
| ||
| ||
the pins completely into the anchor bolts with a hammer. |
| |
|
| |
(Fig.13) |
|
|
|
|
|
Wall |
6mm |
60 to 70mm
12.7mm
13