2. Continue Adding Flue Components

Refer to Cinch Pipe and Termination Cap installation in- structions.

Continue adding flue components, locking each succeed- ing component into place.

Ensure that each succeeding flue component is secure- ly fitted and locked into the preceding component in the flue system. Securing pipe sections with a maximum of two screws is recommended.

90° elbows may be installed and rotated to any point around the preceding component’s vertical axis. If an el- bow does not end up in a locked position with the pre- ceding component, attach with a minimum of two (2) sheet metal screws.

3.Install Support Brackets

Refer to Cinch Pipe and Termination Cap installation in- structions.

HEAT SHIELD

TRIM HEAT SHIELD IF TOO LONG, ADD TO SHIELD IF TOO SHORT

EXTERIOR

FIRESTOP

INTERIOR

FIRESTOP

Figure 20. Heat Shield, Interior & Exterior Firestops

For Vertical Runs - One ceiling firestop is REQUIRED at the hole in each ceiling through which the flue passes.

4. Install Firestops

For Horizontal Runs - Firestops are REQUIRED on both sides of a combustible wall through which the flue passes.

NOTE: Model DVP-TRAP does not need an exterior firestop on an exterior combustible wall. The firestop is built into the cap.

To install firestops for horizontal runs that pass through either interior or exterior walls:

• Cut a 10” x 12” (254mm X 305mm) hole through the wall.

NOTE: The center of the hole is one (1) inch (25.4mm) above the center of the horizontal flue pipe.

Position the firestops on both sides of the hole previ- ously cut and secure the firestops with nails or screws.

To install firestops for vertical runs that pass through ceilings:

Position a plumb bob directly over the center of the verti- cal flue component.

Mark the ceiling to establish the centerpoint of the flue.

Drill a hole or drive a nail through this centerpoint.

Check the floor above for any obstructions, such as wir- ing or plumbing runs.

Reposition the fireplace and flue system, if necessary, to accommodate the ceiling joists and/or obstructions.

Cut an 10-inch X 10-inch (254mm x 254mm) hole through the ceiling, using the centerpoint previously marked.

• The heat shields of the firestops MUST BE placed to-

• Frame the hole with framing lumber the same size as the

wards the top of the hole.

ceiling joists.

• Continue the flue run through the firestops.

NOTE: There must be NO INSULATION or other

10" (254mm)

combustibles inside the framed firestop opening.

10" (254mm)

 

 

10"

 

 

CHIMNEY

 

 

 

HOLE

 

INTERIOR

 

 

 

 

WALL SHIELD

 

 

 

 

 

 

NEW

EXISTING CEILING

 

 

 

JOISTS

 

 

 

FRAMING

 

 

 

 

 

 

 

MEMBERS

 

 

 

12"

CEILING

 

 

 

 

 

 

 

 

Figure 21. Hole & New Framing Members

 

Figure 19. 10" x 12" Hole and Flue Pipe

 

 

 

28

Heat & Glo • PIER/ST/L&RCOR-HVB-CE2068-900 Rev. H • 6/07

 

Page 28
Image 28
Hearth and Home Technologies RCOR-HVB-CE, PIER-HVB-CE, ST-HVB-CE Continue Adding Flue Components, Install Support Brackets