Maintenance

5.0MAINTENANCE

5.1Test, Replacement and Disposal of Batteries

The Liebert® GXT3is designed to allow the user to replace the internal battery pack safely. Refer to Table 7 for internal battery pack part numbers for Liebert GXT3 UPS and Liebert External Battery Cabinets:

Table 7

Replacement battery pack

 

 

 

 

 

 

 

Replacement Internal Battery

Quantity

Unit Type and Model #

Pack Model Number

Required

Liebert UPS GXT3-10000T220

GXT3-240BATKIT

2

 

 

 

Liebert External Battery Cabinet

GXT3-240BATKIT

2

GXT3-240VBATTCE

 

 

Read all safety cautions before proceeding. Contact your local dealer or Emerson representative to obtain the part number and pricing of the appropriate replacement battery pack.

Disposal of the UPS and batteries should be carried out by a certified disposal company—observe all local regulations and laws. Lead-acid batteries are classified as harmful toxic waste and as such the law demands that they be disposed of by an authorized recycling centre.

The typical battery lifecycle is 3 to 5 years at an ambient temperature of 25 C, but is also dependent on the frequency and duration of utility failures.

The BATTERY TEST (see 4.8.2 - Battery Test) should be run periodically (6 to 12 months) to ascertain the general condition of the batteries and ensure maximum run time.

5.2Storage

For extended storage at ambient temperatures cooler than 25°C (77°F), the batteries should be charged for 24 hours once every six months.

Connect the UPS to a utility outlet socket having a ground (earth) connection and ensure the miniature circuit breaker is closed. If charging batteries with fixed utility connections, make connections in accordance with 3.0 - Installation.

After 24 hours, disconnect the UPS from the utility supply.

5.3Cleaning

The UPS may be cleaned by wiping it off with a dry cloth. Do not use liquids or solvents.