1. Terminals for connection liquid soap pumps
2. Neutral line
3. Soap signals
Fig. 4.7.B. Electrical connection soap pumps
4.8. PREPARING THE MACHINE FOR OPERATION
CHECKING BEFORE PUTTING INTO SERVICE
1.Make sure the transporting braces are removed.
2.Put out all things from wash drum.
3.Check the machine horizontal position.
4.Check connection and clearance of your drain, channel or central drainage.
5.Check protective connection (earthing) and electrical supply connection.
6.Open water valves to machine and check hose and connections for leaks.
7.Read carefully the „User´s manual“ and „Programming manual“, which are a part of delivery.
8.Initialize the programmer after machine installation. The calibration of the zero level must not happen anymore. This calibration is executed in the factory and is not changeable.
9.Check the drum rotation direction during extracting according to the extracting label.
10.Check the vibration switch function during extracting (see also chapter 5.2 adjustments and parts exchange, adjustment of the vibration switch.
11.Check the emergency function.
18 | INSTALLATION AND MAINTENANCE MANUAL | PUBLICATION DATE Sep 05 100646 |