Link Test

The Link Test is a test for measuring the throughput and efficiency of the RF link between two Canopy modules.

To perform a link test enter a number into the field labeled “Duration”. The duration is the number of seconds the RF link will be tested. Start the link test by clicking the “Start Test” button. The test will now run for the set duration. If the web page is not set to automatically refresh, click the “Refresh Display” button to see the results. For a Canopy System link to be considered acceptable it is necessary for the efficiencies of the link test to be greater than 90% in both the uplink and downlink direction. It is recommended that when a new link is installed that a link test be executed to ensure that the efficiencies are within recommended guidelines.

The key fields are:

 

 

Downlink RATE, bits per second

Downlink Efficiency, percent

Uplink RATE, bits per second

Uplink Efficiency, percent

Time & Date

This web page is utilized to set the time and date of the access point module when it is not connected to a Cluster Management Module (CMM). The time and date would need to be set every time there is a power cycle. The format for the entry is:

Time: hh:mm:ss Date: mm/dd/yyyy

hh: two digit hour in military time

mm: two digit minute

ss: two digit second

mm: two digit month

dd: two digit day

yyyy: four digit year

Enter in the appropriate information and click the Set Time and Date button.

Page 37
Image 37
Motorola Canopy Backhaul Module user manual Link Test, Time & Date