![](/images/new-backgrounds/1041925/41925119x1.webp)
APPENDIX — ST-45 PUMP SLUMPTEST PROCEDURE
1.To obtain a representative sample (concrete), take sev- eralsamplesatthreeormoreregularintervalsthroughout thedischargeofthemixerortruck.DONOTtakesamples at the beginning or end of the discharge.
2.Dampen the inside of the cone and place it on a smooth, moist, nonabsorbent, level surface large enough to ac- commodate both the slumped concrete and the slump cone. Stand on the “foot pieces” throughout the test procedure to hold the cone firmly in place.
3.Fill the cone 1/3 full by volume (Figure
4.Fill cone another 1/3 (Figure
5.Fill cone to overflowing (Figure
6.Remove the excess concrete (Figure
7.Lift the cone vertically (Figure
8.Lay a straight edge (Figure
BULLET POINTED
STEEL ROD
1/3 FULL
1/2 DIAMETER
24 INCHES LONGFOOT PIECE
Figure 41-A. SlumpTest (1/3 Full)
Figure 41-B. Slump
Test (2/3 Full)
2/3 FULL
Figure 41-C. SlumpTest
(Full-Overflow)
FULL (OVERFLOW)
Figure 41-D. SlumpTest
(Removing Excess Concrete)
Figure 41-E. SlumpTest
(Cone Invert)
Figure 41-F. SlumpTest
(Measurement)