3.Install the high pressure pipe to the heat exchanger liquid pipe, and the low pressure pipe to the
heat exchanger gas pipe respectively using the flare nut, taking care not to cause any leakage of refrigerant.
4.Be sure to insulate the pipe with appropriate insulation material.
5.Insert the drain hose into the drain pipe, and connect them by tying them to the cable tie to prevent any water leakage.
6.After completion of the installation, check the connecting area for any gas leakage.
7.Wind a finish tape when the wiring of the refrigerant pipe, the unit, and the drain piping are completed.
Outdoor unit
checking area
Indoor unit checking area