Installation Manual

IMN

TigerAccess™ EE

 

 

 

3 Setting Up the Rack

When setting up the rack, you must first install the rack and then the system. Refer to the assembly documents.

3.1Rack Installation

The switch is designed for indoor operation in the central office or collocation room with controlled environmental conditions. The network equipment is located in a central office. Each type of location is characterized by a typical technical infrastructure.

Doors and rear panels are not provided. Additional components are needed to adapt the network equipment on the existing infrastructure.

The technical infrastructure of a central office is characterized by:

Power supply 100-240VAC, 50/60Hz

Indoor conditions: (see environmental conditions in the system description)

Short interconnections to other equipment

The dimensions of the racks are shown in Tab. 3.1.

Rack Type

Height

 

 

19”

2200 mm (86.6 in)

 

 

ETSI1)

2200 mm

 

 

Width

600 mm (23.6 in)

600 mm

Depth

400 mm (15.7 in)

300 or 600 mm

1) ETSI rack mount kit is needed (See Tab. 6.1).

Tab. 3.1 Rack Type Measures

3.2Constructing the Rack

i

To construct the rack:

1.Erect and secure the rack.

Use the assembly documents for installing the rack.

Be sure to consult your rack configuring documentation when positioning and securing the rack.

2.Ground the rack.

The rack and the system must always be grounded. In unmeshed buildings, the rack is grounded by attaching it to a secure grounding source where indicated with the symbol in Fig. 3.1. Be sure that it is tightly fastened with the screws provided.

Fig. 3.1 Grounding Symbol

SMC7824M/VSW

19

Page 20
Image 20
SMC Networks SMC7824M/VSW manual Setting Up the Rack, Rack Installation, Constructing the Rack