AOC-19 Maintenance Arrangements
| Ref: CAR 726.08(v) |
|
|
|
|
|
|
|
|
|
|
13. | Have the applicability and authority | N/A | OK | Finding | Not Checked |
| of the publications been delineated |
|
|
|
|
| in the contract? |
|
|
|
|
| ∙ Has the operator adopted any |
|
|
|
|
| contract facility processes, |
|
|
|
|
| i.e. repair methods and/or |
|
|
|
|
| techniques? |
|
|
|
|
| Ref: CAR 726.08(v) |
|
|
|
|
|
|
|
|
|
|
14. | Does the contract state the | N/A | OK | Finding | Not Checked |
| responsibilities and involvement of |
|
|
|
|
| both parties in all or part of the |
|
|
|
|
| reliability program? |
|
|
|
|
| ∙ Is the operators fleet |
|
|
|
|
| combined with the contractors |
|
|
|
|
| aircraft for reliability and |
|
|
|
|
| statistical purposes? |
|
|
|
|
| ∙ Do the aircraft operate in |
|
|
|
|
| similar environments? |
|
|
|
|
| Ref: CAR 726.08(v) |
|
|
|
|
|
|
|
|
|
|
15. | Does the contractor subcontract to | N/A | OK | Finding | Not Checked |
| a third party any part of the work? |
|
|
|
|
| ∙ Where actioned, does the |
|
|
|
|
| main contract identify the |
|
|
|
|
| contracting responsibilities |
|
|
|
|
| between the operator and the |
|
|
|
|
| first AMO? |
|
|
|
|
| ∙ Have all phases of the |
|
|
|
|
| subcontractor's arrangements |
|
|
|
|
| been investigated using the |
|
|
|
|
| same procedures as for the |
|
|
|
|
| main contractor? |
|
|
|
|
| Ref: CAR 726.08(v) |
|
|
|
|
|
|
|
|
|
|
16. | Is the contract significant enough | N/A | OK | Finding | Not Checked |
| to warrant Transport Canada |
|
|
|
|
| review? |
|
|
|
|
| Ref: CAR 726.08(v) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| March 2001 |
|
|
| Page 84 |