Step 2: Installation
1.Uncrate carefully. Report any hidden damage to the freight carrier IMMEDIATELY.
2.Do not remove any tags or labels until unit is installed and working properly.
3.If unit is to be installed on legs, locate legs and install as shown in Figure 2 below.
Figure 2 | INSTALLATION |
|
4.If the unit is to be installed on a counter top or other surface without using legs, the unit must be sealed to the surface to prevent any water, grease, etc., from accumulating under the steamer. The steamer can be bolted to the counter but will still have to be sealed. The installer may use G.E. or Dow Corning RTV type sealant. Consult local code for exact requirements. See Figure 3 on next page.