7.1. Transport and Packing

»Please ensure adequate carrying capacity of the lifting equipment.

The equipment pass a rigorous operating test in the factory and are packed carefully to avoid transport damage.

Please check packing on delivery for transport damage.

The inlet and discharge flanges are sealed with plugs, so that no dirt can enter during transport. Plugs must be removed before assembly.

Packing materials should be disposed of according to environmental laws or reused.

Only use for transport of the equipment a suitable lifting device (e. g. a fork lift truck or a workshop crane).

For transport of control cabinets fasten the transport cables to the eyelets of the control cabinets Transport must be shock-proofed and free from vibrations.

7.2. Assembly

»Please ensure adequate carrying capacity of the lifting equipment.

Check the carrying capacity of the point of installation, particularly if installed on a platform.

The place selected for installation should be as free of vibrations as possible.

The main switch must be freely accessible.

Ground the equipment against electrostatic charging.

7.3. Storage

Between delivery and machine commissioning the equipment should be stored in a dry, dust-free and vibration-free room.

The control system may only be stored at temperatures from -25 to +55°C (-13 to +131 °F).