29
Models 8752, 8756, 8757 Operating Procedures
080820
SanitizingStep 1
Preparea pail of approved 100 PPM sanitizingsolution
(examples: 2- 1/2 gal. [9.5 liters] of Kay- 5Ror 2 gal.
[7.6 liters] of Stera- SheenR). USE WARM WATER
ANDFOLLOW THE MANUFACTURER’S SPECIFIC-
ATIONS.Place the pail of sanitizing solution inside the
mix cabinet.
Step 2
Brush clean the mix inlet tube with the long brush and
sanitizing solution.
Figure 33
Step 3
Connect the free end of the flare line t o the threaded
fitting on the mix inlet tube.
Figure 34
Step 4
Install the pressure line. Attach the quick disconnect
fitting of the pressure line to the other fitting on the mix
inlet tube just above the flare line and allow the other
end to hang free.
Figure 35
Step 5
Insert the free end of the suction line and pressure line
into the pail of sanitizing solution.
Figure 36
Step 6
Place the power switch in the ON position.