25
Model C300 NP Operating Procedures
Step 11
Place a pail beneath the door spout. Open the draw
valve and drain the freezing cylinder to remove any
incorrectly brixed product. Close the draw valve.
Step 12
Hold a large cup under the prime plug port on the
door, until the liquid level (not foam) reaches
1/4-3/8” (6-9 mm) below the prime hole. Press the
OFF (<- -) key and then close the prime plug.
Step 13
Press the BEATER (- - -) key. Let the unit run in the
BEATER mode for one minute. Press the OFF (<- -)
key.
Step 14
Press the PRIME (+ + +) key. Allow the liquid level
to fill to the primeplug hole
Repeat Steps1 through 14 for the other f reezing
cylinder.
Step 15
To place the freezing cylinders in the AUTO mode,
press the AUTO (- ->) key on both sides. When the
unit cycles off, the product will be at serving
viscosity.
Figure 35
Step 16
Close the lighted display when complete. Replace
the panels and the hood, and attach with screws.
Install the front drip tray and the splash shield on t he
front of the freezer.
120 Day Closing Procedure
We recommend that the machine be completely
disassembled and cleaned at least every 120 days
using the following procedures.
ALWAYS FOLLOW LOCAL HEALTH CODES
To disassemble the Model C300, the following items
will be needed:
STwo cleaning pails
SNecessary brushes (provided with freezer)
SCleaner
SSingle service towels
Draining Product From theFreezing Cylinder
Step 1
Press the BEATER (- - -) key. This will allow the
beater to operate to push the product from the
freezing cylinder. Open the draw valve and drain the
product from the machine.
Figure 36