N. FURNACE CHECKOUT PROCEDURE

Before any system of gas piping is finally put into service, it shall be carefully tested to assure that it is gas tight as indicated in section IV. H. Gas Piping of this manual.

NOTICE: All controls on the unit should be checked for proper functioning prior to the qualified service personnel leaving the job site. Specifically the following should be checked:

With furnace in normal heating operation, check to make certain blower will start and stop automatically under control of integrated fan control.

1.Check safety limit control as follows:

a.Shut off incoming power.

b.Block return air opening or disconnect blower motor leads.

c.Restore power to furnace.

d.Set thermostat above room temperature calling for heat.

e.When high air temperatures are reached in furnace at limit control setting with blower out of operation, burner should shut off.

f.Shut off electrical power.

IMPORTANT: Remove blockage or reconnect blower motor and restore power.

2.Make certain thermostat will automatically start and stop furnace.

3.Block the flue pipe outlet gradually until the pressure switch functions shutting off the main burners.

4.Block the inlet gradually until pressure switch functions shutting off the main burners.

IMPORTANT: Remove flue or air inlet blockages when done.