All installations and services must be performed by qualified service personnel.
B.CAD CELL CHECKOUT PROCEDURE:
1.Remove cad cell lead wires, then start the burner. Shortly after burner starts, place a temporary jumper between terminals f & f of the oil primary control. Connect ohmmeter across cad cell lead wires - resistance should be less than 1600 ohms.
2.Stop the burner and remove temporary jumper.
3.With the burner off, check dark cell resistance across cad cell lead wires. Resistance should be greater than 20,000 ohms. If cell resistances are different from above, recheck wiring, location of cell, etc. If necessary, replace plug in portion of cell, (Part No. 350104).
4.Reconnect cad cell lead wires. Check out the oil primary control according to the instructions packed with the control.
C.HEAT EXCHANGER CLEANING INSTRUCTIONS
: The heat exchanger must be cleaned by a qualified service person.
For
To clean the heat exchanger,
1.First, turn off all power to the unit.
2.Remove cleanout plugs, the vent connector pipe to the chimney, the burner and the burner mounting plate.
3.With access to the inside of the heat exchanger through the burner cleanout openings and the vent pipe connection, it is now possible to use a long, flexible wire brush and an
NOTE: A one inch (outside diameter) vacuum cleaner hose will fit into the radiator.
39