Normal Heat
Cycle Operating
Sequence
NOTE: All LED Flash Codes are on page 38.
Switch Settng Chart for Fan
OFFDelay (See SW1 on W.D.)
TIME SW1 SW2
90 sec | OFF | ON |
120 sec | OFF | OFF |
160 sec | ON | OFF |
45 sec | ON | ON |
Abnormal Heat Cycle Functions
1)Call for Heat - The thermostat calls for heat by energizing the “W” terminal. The control checks to see that the limit and high limit switches are closed and the heat section pressure switch is open and the main combustion air pressure switch (Sizes 800 and 1200) is open. If the limit or high limit switch is open, the control responds as defined in the “Abnormal Heat Cycle, Limit Switch Operation”. If the heat section pressure switch or main combustion air pressure switch are closed, the control will do four flashes on the green LED and wait indefinitely for the heat section pressure switch or main combustion air pressure switch to open. If the heat section pressure switch and main combustion air pressure switch are open, the control proceeds to prepurge.
2)Prepurge - The control energizes the heat section venter motor and main venter motor (Sizes 800 and 1200) and waits for the heat section pressure switch and main combustion air pressure switch to close. If the heat section pressure switch or main combustion air pressure switch does not close within 30 seconds of the heat section venter motor and main venter motor energizing, the control will do two flashes on the green LED. The control will leave the heat section venter motor and main venter motor energized indefi- nitely as long as the call for heat remains and the heat section pressure switch or main combustion air pressure switch is open.
When the heat section pressure switch and main combustion air pressure switch are proven closed, the control begins the prepurge time. If flame is present any time while in prepurge, the prepurge time is restarted. If flame is present long enough to cause lockout, the con- trol responds as defined in “Fault Modes, Undesired Flame”.
The control runs the heat section venter motor and main venter motor for a 20 second prepurge time, then proceeds to the ignition trial period.
3)Ignition Trial Period - The control energizes the spark and main gas valve. The venter remains energized. If flame is sensed during the first 16 seconds, the spark is
4)Fan On Delay - The control waits for 30 seconds from the time the gas valve opened and then energizes the fan motor. The gas valve, heat section venter motor, and main venter motor remain energized. The control proceeds to steady heat mode.
5)Steady Heat - Control inputs are continuously monitored to ensure limit, high limit, heat section pressure switch, and main combustion air pressure switch are closed, flame is established, and the thermostat call for heat remains. When the thermostat call for heat is removed, the control
6)Post Purge - The heat section venter motor and main venter motor outputs remain on for a 45 second
7)Fan Off Delay - The fan motor is
Interrupted Thermostat Call for Heat - If the thermostat demand for heat is removed before the flame is recognized, the control will run the heat section venter motor and main venter motor for the post purge period and
If the thermostat demand for heat is removed after successful ignition, the control will
Ignition Retry - If flame is not established on the first trial for ignition period, the control