![MAIN BURNERS](/images/new-backgrounds/65904/6590413x1.webp)
GR SERIES GAS FRYERS - REMOVAL AND REPLACEMENT OF PARTS
5.Remove the capillary tube retaining and packing nuts, from the bottom of fry tank.
6.Remove screws securing capillary tube mounting clips to the fry tank heat tube then remove capillary tube.
7.Reverse procedure to install.
MAIN BURNERS
WARNING: DISCONNECT THE
ELECTRICAL POWER TO THE
MACHINE AND FOLLOW LOCKOUT /
TAGOUT PROCEDURES.
WARNING: SHUT OFF THE GAS BEFORE SERVICING THE UNIT.
1.Open fryer door.
2.Remove main burner shipping ties (if installed).
NOTE: All shipping ties should be removed during installation. Do not replace for normal operation.
3.Lift main burner up and tilt the top of burner toward fry tank until it clears the gas orifice at the bottom.
A. Lift main burner from fryer.
NOTE: The main burners mount to the fryers’ burner mounting bracket by shoulder bolts that rest in the keyway slot.