8 Check-out procedure — checklist
❏Boiler and heat distribution units filled with water?
❏Automatic air vent, if used, open one full turn?
❏Air purged from system?
❏Air purged from gas piping? Piping checked for leaks?
❏Correctly sized manifold orifices installed? Refer to manual Section 2a to check size and fuel type.
Correctly sized manifold orifices must be used. Failure to do so will cause severe personal in- jury, death or substantial property damage.
❏Followed operating instructions on boiler or in manual Section 9 for proper
❏Verify that the boiler switches to high fire after 60 seconds of main flame operation.
❏Proper burner flame observed at high fire? Refer to Check burner flame, manual Section 7b.
❏Test limit control — While burners are operating, move indicator on limit control below actual boiler water tem- perature. Burners should go off while circulator continues to operate. Raise setting on limit control above boiler water temperature and burners should reignite.
❏Test additional
❏Test ignition system safety device:
a.Connect manometer to outlet side of gas valve.
b.Start boiler, allowing for normal
c.With main burners on, manually shut off gas supply at manual main shutoff gas valve. Burners should go off.
d.Open manual main shutoff gas valve. Manometer should confirm there is no gas flow.
e.Pilot will relight, flame sensing element will sense pilot flame and main burners will reignite.
❏Set limit control(s) to system temperature requirements. Adjust balancing valves and controls to provide design temperature to system.
❏For multiple zones, adjust flow so it is about the same in each zone.
❏Verify thermostat heat anticipator (if available) set properly?
Refer to Field wiring, manual Section 6, Thermostat(s).
❏Cycle boiler with thermostat — Raise to highest setting and verify boiler goes through normal
❏Measure natural gas input:
a.Operate boiler 10 minutes.
b.Turn off other appliances.
c.At natural gas meter, measure time (in seconds) re- quired to use one cubic foot of gas.
d.Calculate gas input:
e.Btuh calculated should approximate input rating on boiler rating label.
❏Check manifold gas pressure by connecting manometer to downstream test tapping on main gas valve. Manifold pres- sure for natural gas should be 3.5" w.c. and for propane gas should be 10" w.c.
❏Observe several operating cycles for proper operation.
❏Set room thermostat to desired room temperature.
❏Fill in Installation and service certificate below?
❏Review all instructions shipped with this boiler with owner or maintenance person. Return instructions to envelope and give to owner or place in pocket inside front panel in boiler.
Installation and service certificate
Boiler model __________________ Series __________ CP number ___________ Date installed ___________
Measured Btuh input ____________________ | ❏ Installation instructions have been followed. | ||
|
| ||
|
| ❏ Check out sequence has been performed. | |
|
| ❏ Above information is certified to be correct. | |
|
| ❏ Information received and left with owner/maintenance person | |
Installer ________________________ | ________________________________ | ________________________ | |
(company) |
| (address) | (phone) |
Installer’s signature: _____________________________________