Unigreen Super Spalliera, Ventagli, Minibar, RV-GDC manual Filling the Tank, Test with Clean Water

Page 14

FIG. 10

FIG. 11

FIG. 12

WARNING: using the taps on the pump or in any case on the front of the machine puts the operator near the cardan shaft. Despite the presence of CE standard protective covers you should take great care.

4.10 FILLING THE TANK

The machines for defensive crop treatments, in consideration of the safety of persons, animals and the protection of the environment, must only be filled indirectly from open water courses and only by free-falling water from the waterworks.

The pipe used for filling must never come into contact with the liquid inside the tank and therefore the water must always fall over the upper edge of the filling inlet and through the filter installed on it.

The tank is fitted with a transparent graduated band that shows the exact quantity of liquid inside. This reading is precise if the tank is on flat ground; the actual total capacity coincides with the highest number. All the filling systems fitted by Unigreen on their production machines or on request are antipollution and stop the liquid overflowing out of the tank.

a)FILLING WITH THE 3-WAY DEVIATOR (Fig. 10- Fig. 11).

It is possible to fill the tank using the pump and the floating filter kit G (cod.1002/ 0080F) with 6 metres of rubber hose (the floating filter lets you always and only suck up clean water).

=connect hose T to deviator D using the union hose adaptor supplied.

=turn the lever of deviator D to the filling position.

=place the other end of the hose, on which you fitted filter G, in the watering point.

=start the power-takeoff leaving pressure regulator C in the draining position (you don’t have to put the pump under pressure).

=the filling speed in litres/minute is equal to the delivery of pump P.

=visually check the level of the liquid in the tank and after filling stop the pump and put the lever of deviator D back in the working position.

=disconnect pipe T from deviator D.

b)FILLING WITH THE SUCTION FILTER (Fig. 3- Fig. 11).

If the 3-way deviator isn’t fitted you can fill the tank using the coupling on the cover of the suction filter. Unscrew the rear wing nut of the filter and using a G1"1/2 threaded union, connect pipe T with the floating filter to the coupling.

Also in this case the filling speed in litres/minute is equal to the delivery of the pump.

c)FILLING WITH THE ANTIPOLLUTION EJECTOR (Fig. 12)

If you are filling with an antipollution hydroejector (mounted as standard on some models) then you should proceed as follows:

=put roughly 20-30 L of water in the tank and start the pump.

=remove the cap of ejector E and insert filling pipe T.

=place the other end of the hose, on which you fitted filter G, in the watering point.

=open the tap that supplies the ejector (on auxiliary taps, see point 4.9).

=increase the pressure until it reaches a value which is sufficient to suck up the liquid.

=visually check the level of the liquid inside the tank and after filling disconnect pipe T from the ejector, close the tap and replace the cap.

4.11 TEST WITH CLEAN WATER

It is good practice to do a test with clean water (without chemical product in the tank) before the first treatment to make sure the mistblower is working properly and to get to know the controls. For instructions on how to proceed with the treatment see the chapter SPRAYING.

14unigreen

Image 14
Contents USE and Maintenance Manual 09/2006Summary Hand Lances Maintenance Composition of the Manual Using and Keeping the USE and Maintenance ManualGuarantee Product Responsibility Unigreen spa is not responsible ifKey to the symbols Prohibited USE Using Chemical ProductsIntended USE Regulations for the USE of Chemical ProductsDriving on the Road Characteristics and SpecificationsWeather Conditions Tables of Fittings AllowedInstructions Noise Level of the MachineStandards of Reference Description of the MachineTowed Atomisers Parking Preliminary ChecksTransporting and Moving the Machine For verification use the formula shown here Tractor CouplingTHREE-POINT Coupling Hydraulic Connection to the DistributorsSuction Filter Cardan ShaftPump Control box for GCP Elettrico electrical regulators Pressure RegulatorComponents of the Pressure Regulator General InstructionsTank rinsing Ejector Agitator Delivery Filters only Equipped ModelsAuxiliaries Taps Block Test with Clean Water Filling the Tank12.2PREMIXER on Cover Optional MixingManual Premixing 12.4COVER Washer for Chemical ContainersWashing the Atomiser 13.1CIRCUIT Washer and Tank WasherClutch Blower GroupMultiplier FAN Unit Super Spalliera for Espalier Ventagli Fans CANOPY, and Espalier DistributorsMinibar for Espalier OIL Feed from Tractor for hydraulic systems RV Boom for GDCHydraulics RV per GDCDescription of the MFC Nozzles Spraying Description of the DiffusersNON-DRIP Valve Mistblower CalibrationBatching Taps see Picture Calibrated Plates CPRoutine Maintenance MaintenanceProgrammed Maintenance Cleaning the NozzlesMultiplier Lubrication Extraordinary MaintenancePutting Back Into Service After Winter Layup RepairsElectrical and Electronic Apparatus Waste Eeaw Demolition and DisposalMaterials for Demolition Airdrop Calibrating Tables Tables for Calibrating Airdrop 2 Ventagli FansOptional Tables for Calibrating Airdrop 2 Ventagli + TOP DiffusorsPiastrina Calibrata Tables for Calibrating Airdrop MinibarTables for Calibrating Airdrop Super Spalliera Tables for Calibrating Airdrop RV-GDCTables of Delivery of Nozzles for Hand Lances Table of Programmed Maintenance Operation 50 h 300 hTAB.18A Allowed Fittings TAB aMember of the group