Genie DPL-35S, DPL-30S manual Pre-operation Inspection, Breather Cap AC & DC Models, Fundamentals

Page 11

Second Edition • First Printing

Operator’s Manual

 

 

 

 

Pre-operation Inspection

Do Not Operate Unless:

You learn and practice the principles of safe machine operation contained in this operator’s manual.

1Avoid hazardous situations.

2Always perform a pre-operation inspection.

Know and understand the pre-operation inspection before going on to the next section.

3Always perform the function tests prior to use.

4Inspect the workplace.

5Only use the machine as it was intended.

Breather Cap - AC & DC Models

Component damage will occur if the machine is operated without a breather cap.

The first time this machine is set up for use, the pipe plug in the hydraulic reservoir, under the battery cover, must be removed and permanently replaced with a breather cap.

A breather cap is supplied and can be found in an envelope taped to the mast.

Fundamentals

It is the responsibility of the operator to perform a pre-operation inspection and routine maintenance.

The pre-operation inspection is a visual inspection performed by the operator prior to each work shift. The inspection is designed to discover if anything is apparently wrong with a machine before the operator performs the function tests.

The pre-operation inspection also serves to determine if routine maintenance procedures are required. Only routine maintenance items specified in this manual may be performed by the operator.

Refer to the list on the next page and check each of the items.

If damage or any unauthorized variation from factory delivered condition is discovered, the machine must be tagged and removed from service.

Repairs to the machine may only be made by a qualified service technician, according to the manufacturer's specifications. After repairs are completed, the operator must perform a pre-operation inspection again before going on to the function tests.

Scheduled maintenance inspections shall be performed by qualified service technicians, according to the manufacturer's specifications and the requirements listed in the responsibilities manual.

Part No. 82799

Genie DPL Super Series

9

Image 11
Contents Operator’s Manual Contact us ContentsDo Not Operate Unless Safety RulesTip-over Hazards Fall Hazards Component Damage Hazards Electrocution HazardsCollision Hazards Decal Legend Improper Use HazardDamaged Machine Hazards Bodily Injury Hazard Lifting Hazard Battery and Charger Safety DC Models Burn Hazards Explosion Hazards Platform Controls ControlsPage Fundamentals Pre-operation InspectionBreather Cap AC & DC Models Pre-operation Inspection Observe and Obey MaintenanceCheck the Hydraulic Oil Level AC and DC Models Check the Battery DC ModelsScheduled Maintenance Function Tests Function TestsTest Emergency Stop Test Outrigger Interlock Workplace Inspection Workplace InspectionOperating Instructions Platform Raise and Lower SetupEmergency Stop Fall Protection Platform Overload Indicator Light if equippedManual Lowering Auxiliary Platform Lowering AC & DC ModelsDry Battery Filling Charging Instructions Battery and Charger Instructions Observe and ObeyTo Charge Battery Winching the Machine onto a Flatbed Truck Transport and Lifting InstructionsLoading the Machine With a Forklift Transport and Lifting Instructions Lifting InstructionsInspection for Decals with Words DecalsDecals Inspection for Decals with Symbols Decals Maximum capacity SpecificationsDistributed By