Genie DPL-25S, DPL-30S, DPL-35S manual Tip-over Hazards

Page 4

Operator’s Manual

Second Edition • First Printing

 

 

 

 

SAFETY RULES

Tip-over Hazards

Do not raise the platform unless the base is level, all four outriggers are properly set up and the leveling jacks firmly contact the ground.

Do not move the machine while the platform is raised.

Do not adjust or remove the outriggers while the platform is occupied or raised.

Do not place or attach overhanging loads to any part of this machine.

Do not transport tools and materials unless they are evenly distributed and can be safely handled by person(s) in the platform.

Do not use the machine on a moving or mobile surface or vehicle.

Do not operate the machine in strong or gusty winds. Do not increase the surface area of the platform or the load. Increasing the area exposed to the wind will decrease machine stability.

Occupants, equipment and materials shall not exceed the maximum platform capacity.

Maximum capacity - DPL-25S

Do not raise the platform unless the machine is level. Do not set the machine up on a surface where it cannot be leveled using only the outriggers.

Do not place ladders or scaffolds in the platform or against any part of this machine.

Do not push off or pull toward any object outside the platform.

Maximum allowable

 

 

manual force

90 lbs

400 N

ANSI and CE

750 lbs

340 kg

 

 

 

CSA

600 lbs

272 kg

 

 

 

Maximum occupants

 

2

 

 

 

Maximum capacity - DPL-30S

 

 

 

 

 

ANSI and CE

750 lbs

340 kg

 

 

 

CSA

600 lbs

272 kg

 

 

 

Maximum occupants

 

2

 

 

 

2

Genie DPL Super Series

Part No. 82799

Image 4
Contents Operator’s Manual Contents Contact usSafety Rules Do Not Operate UnlessTip-over Hazards Fall Hazards Collision Hazards Electrocution HazardsComponent Damage Hazards Improper Use Hazard Damaged Machine HazardsBodily Injury Hazard Decal LegendExplosion Hazards Battery and Charger Safety DC Models Burn HazardsLifting Hazard Controls Platform ControlsPage Breather Cap AC & DC Models Pre-operation InspectionFundamentals Pre-operation Inspection Maintenance Observe and ObeyCheck the Battery DC Models Check the Hydraulic Oil Level AC and DC ModelsScheduled Maintenance Function Tests Function TestsTest Emergency Stop Test Outrigger Interlock Workplace Inspection Workplace InspectionOperating Instructions Emergency Stop SetupPlatform Raise and Lower Platform Overload Indicator Light if equipped Manual LoweringAuxiliary Platform Lowering AC & DC Models Fall ProtectionTo Charge Battery Battery and Charger Instructions Observe and ObeyDry Battery Filling Charging Instructions Loading the Machine With a Forklift Transport and Lifting InstructionsWinching the Machine onto a Flatbed Truck Lifting Instructions Transport and Lifting InstructionsDecals Inspection for Decals with WordsDecals Inspection for Decals with Symbols Decals Specifications Maximum capacityDistributed By