Bryant ASPAX1BBA015 owner manual Service Schedule, Be performed by the nearest dealer

Page 23

Section 4 — Maintenance

15 kW Generator

4.13 SERVICE SCHEDULE

ATTENTION: It is recommended that all service work

be performed by the nearest dealer.

 

SYSTEM/COMPONENT

 

PROCEDURE

 

FREQUENCY

 

 

X = Action

Inspect

Change

Clean

W = Weekly

 

 

R = Replace as Necessary

 

 

 

M = Monthly

 

 

* = Notify Dealer

 

 

 

Y = Yearly

 

 

if Repair is Needed.

 

 

 

 

 

 

FUEL

 

 

 

 

 

 

Fuel lines and connections*

X

 

 

M

 

 

LUBRICATION

 

 

 

 

 

 

Oil level

X

 

 

M

 

 

Oil

 

X

 

AFTER BREAK-IN,

 

 

 

 

 

 

AND Y

 

 

Oil filter

 

X

 

AFTER BREAK-IN,

 

 

 

 

 

 

AND Y

 

 

COOLING

 

 

 

 

 

 

Enclosure louvers

X

 

X

W

 

 

BATTERY

 

 

 

 

 

 

Remove corrosion,

X

 

X

M

 

 

ensure dryness

 

 

 

 

 

 

Clean and tighten

X

 

X

M

 

 

battery terminals

 

 

 

 

 

 

Check charge state

X

R

 

EVERY 6 M

 

 

Electrolyte level

X

R

 

EVERY 6 M

 

 

(unsealed batteries only)*

 

 

 

 

 

 

ENGINE AND MOUNTING

 

 

 

 

 

 

Air cleaner

X

R

 

Y

 

 

Spark plug(s)

X

R

 

Y

 

 

GENERAL CONDITION

 

 

 

 

 

 

Vibration, Noise, Leakage,

X

 

 

M

 

 

Temperature*

 

 

 

 

 

 

COMPLETE TUNE-UP*

TO BE COMPLETED BY A DEALER

 

 

 

 

 

 

 

 

 

21

Image 23
Contents Installation Introduction ‹ Contents‹ Operation and Maintenance ‹ HOW to Obtain ServiceIntroduction Inside Front Cover Post Installation Start-up AdjustmentsMaintenance Troubleshooting Warning  ‹ Standards Index  Explosion Hazards System SET LED UNPACKING/INSPECTIONLocation Protection SystemsGfci Generator‹ 1.6.1 Generator SpecificationsFuel Requirements Recommendations Fuel Consumption‹ 1.10.1 Generator Fuel System‹ 1.9.1 15KW, 990CC Engines 10.2.1 15 kW Units Battery InstallationBattery ‹ 1.10.2 Transfer SwitchElectrical Checks Check Transfer Switch OperationBefore Initial START-UP Checking Automatic Operation Generator Tests Under LoadDual Fuel Regulators Adjusting the Regulator Natural GAS only‹ 2.7.1 15 KW Units Voltage Regulator AdjustmentBREAK-IN Procedure ‹ 3.2.2 OFF Position ‹ 3.3.1 12 VDC Accessory OutletAutomatic Transfer Operation ‹ 3.2.1 Auto Position‹ 3.3.2 120 VAC Gfci Outlet ‹ 3.5.1 Transfer to Generator Power SourceSequence of Automatic Operation Manual Transfer Operation‹ 3.7.2 High Temperature Switch Setting the Exercise Timer‹ 3.5.2 Transfer Back to Utility Power Source ‹ 3.7.1 LOW OIL Pressure SwitchChanging the Engine OIL Checking the Engine OIL LevelFuses ‹ 4.5.1 15 KW Generators ‹ 4.3.2 OIL Change ProcedureChanging the OIL Filter Spark PlugsAdjusting Valve Clearance Battery MaintenanceCorrosion Protection Cooling System‹ 4.12.2 Return to Service OUT of Service Procedure‹ 4.12.1 Removal from Service Be performed by the nearest dealer Service ScheduleProblem Cause Correction Troubleshooting GuideMounting Dimensions Electrical Data Customer Connection KW Generator Electrical Schematic Drawing No E9017 SW1 Exploded Views and Parts Lists Part NO. QTY. Description KW Generator Control Panel Drawing No E9162-J Part NO. QTY Description 16B Item Part NO. QTY. Description 138 122 KNOB, AIR Cleaner Views and Parts Lists QTY Description KW Generator Gas Regulator Drawing No D8720-G CASTING, Twin Regulator Housing California and Federal Emission Control Warranty Statement Emission Control System Warranty Warranty Schedule