Bryant ASPAX1BBA015 Voltage Regulator Adjustment, BREAK-IN Procedure, ‹ 2.7.1 15 KW Units

Page 14

Section 3 — Operation

15 kW Generator

2.7ENGINE GOVERNOR ADJUSTMENT

If both AC frequency and voltage are correspondingly high or low, adjust the engine governor as follows:

‹2.7.1 15 KW UNITS

1. Loosen governor clamp bolt (See Figure 2.3).

Figure 2.3 — V-twin Engine Governor

Adjustment

Idle Spring

Governor

Shaft

(Rotate

Clockwise)

2.8VOLTAGE REGULATOR

ADJUSTMENT

With the frequency between 62-63.5 Hertz, slowly turn the slotted potentiometer (Figure 2.5) until line voltage reads 244-252 volts.

NOTE:

Remove the access panel on top of the control panel to adjust the voltage regulator.

Figure 2.5 – Voltage Adjustment Potentiometer

Governor Clamp Bolt

No Load Idle

Adjustment Screw

 

2.Completely remove the idle spring.

3.With governor arm at wide open throttle position, rotate governor shaft fully clockwise. Tighten clamp bolt to 84 inch-pounds.

4.Start unit and apply full load. Use full load speed adjust screw (Figure 2.4) to adjust frequency to 58 Hz.

5.Remove load, stop engine, loosen the idle adjust screw and reconnect the idle spring.

6.Push the governor arm to the closed throttle posi- tion. Make sure the idle spring does not stretch at all.

7.Restart the unit.

8.Slowly turn the idle adjust screw to adjust the no- load idle frequency to 63-63.5 Hz.

9.The governor is now set.

Figure 2.4 — V-twin Full Load Speed Adjust

Screw

Full Load Speed Adjust Screw

12

NOTE:

The voltage regulator is housed above the generator's control panel. The regulator maintains a voltage in direct proportion to frequency. For example, at 62 Hertz, line-to-neutral voltage will be 124 volts.

3.1BREAK-IN PROCEDURE

Once the unit has been installed and all electrical checks have been made, it is strongly recommended that the following “Break-in Procedure” be completed to ensure correct generator operation in the future.

1.Set the generator’s AUTO/OFF/MANUAL switch to AUTO.

2.Turn OFF the utility power supply to the transfer switch using the means provided (such as a utility main line circuit breaker).

3.The unit will start, and the transfer switch will transfer to standby.

4.Using the transfer switch’s built-in emergency load center, turn on circuits to load the generator to approximately 25% rated load and run the unit for one hour.

5.Run the unit for one hour at 50% rated load.

6.Run the unit for one hour at 75% rated load.

7.Run the unit for one hour at 100% rated load.

8.Turn ON the utility power supply to the transfer switch, which will allow the transfer switch to transfer back to utility power. The unit will con- tinue to run for one minute and then shut down.

Image 14
Contents Installation ‹ HOW to Obtain Service ‹ Contents‹ Operation and Maintenance IntroductionTroubleshooting Post Installation Start-up AdjustmentsMaintenance Introduction Inside Front Cover Warning   Explosion Hazards  ‹ Standards IndexProtection Systems UNPACKING/INSPECTIONLocation System SET LEDGenerator GfciFuel Consumption SpecificationsFuel Requirements Recommendations ‹ 1.6.1 Generator‹ 1.10.1 Generator Fuel System‹ 1.9.1 15KW, 990CC Engines ‹ 1.10.2 Transfer Switch Battery InstallationBattery 10.2.1 15 kW UnitsElectrical Checks Check Transfer Switch OperationBefore Initial START-UP Generator Tests Under Load Checking Automatic OperationAdjusting the Regulator Natural GAS only Dual Fuel Regulators‹ 2.7.1 15 KW Units Voltage Regulator AdjustmentBREAK-IN Procedure ‹ 3.2.1 Auto Position ‹ 3.3.1 12 VDC Accessory OutletAutomatic Transfer Operation ‹ 3.2.2 OFF PositionManual Transfer Operation ‹ 3.5.1 Transfer to Generator Power SourceSequence of Automatic Operation ‹ 3.3.2 120 VAC Gfci Outlet‹ 3.7.1 LOW OIL Pressure Switch Setting the Exercise Timer‹ 3.5.2 Transfer Back to Utility Power Source ‹ 3.7.2 High Temperature SwitchChanging the Engine OIL Checking the Engine OIL LevelFuses Spark Plugs ‹ 4.3.2 OIL Change ProcedureChanging the OIL Filter ‹ 4.5.1 15 KW GeneratorsBattery Maintenance Adjusting Valve ClearanceCooling System Corrosion Protection‹ 4.12.2 Return to Service OUT of Service Procedure‹ 4.12.1 Removal from Service Service Schedule Be performed by the nearest dealerTroubleshooting Guide Problem Cause CorrectionMounting Dimensions Electrical Data Customer Connection KW Generator Electrical Schematic Drawing No E9017 SW1 Exploded Views and Parts Lists Part NO. QTY. Description KW Generator Control Panel Drawing No E9162-J Part NO. QTY Description 16B Item Part NO. QTY. Description 138 122 KNOB, AIR Cleaner Views and Parts Lists QTY Description KW Generator Gas Regulator Drawing No D8720-G CASTING, Twin Regulator Housing California and Federal Emission Control Warranty Statement Emission Control System Warranty Warranty Schedule