2.2.7 Mounting of Line/Trunk Card on 1000 IVS PIM

Mount the Line/Trunk cards in the following slots on the Remote PIM. Connect the line cables referring to Figure

3-24through Figure 3-26and Table 3-9.

 

 

 

 

 

 

 

 

LT00

LT01

LT02

LT03

LT04

LT05

LT06

LT07

LT08

 

 

 

 

*1

 

 

 

 

 

 

Remote PIM

 

 

 

 

 

 

 

*2

P

 

 

 

 

 

 

 

 

 

W

 

 

 

 

 

 

 

 

 

R

 

LTC0

 

 

LTC1

 

 

 

LINE/TRUNK

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

CARD

 

 

 

 

 

 

 

 

 

 

 

 

 

 

BWB

 

 

 

 

 

 

 

 

 

 

 

 

FRONT

 

*1 When providing DAIB card only (Max. 23 ports): LT01~LT03slot

*2 When providing one DAIB card and one DAIC card (Max. 4 ports): LT00~LT08 slot (Mounted DAIB in MP, mountedDAIC in LT07 so LT 08 is available for 8 ports card)

*3 When DAIC is mounted in slot 07, slot 06 must use the 4-port Line/Trunk card, so that the last 4 ports of slot 06 do not interfere with the DAIC card and when DK00 can assign on this last 4-ports, the system can have a Max. of 44 ports.

Note 1: The CSI card can not be used on the Remote PIM.

Note 2: One port of the last 24 ports can not be used for line/trunk, because it is used for control signaling channel.

Figure 3-24 Mounting Location of Line/Trunk Card (1000 IVS)

Table 3-9 LTC Connector Accommodation (1000 IVS)

REMOTE PIM TYPE

LTC CONNECTOR

CARD SLOT NUMBER

 

 

 

1000 IVS

LTC0

LT01~LT03

(48 Port PIM)

 

 

LTC1

LT04~LT08, LT00

CHAPTER 3

ND-46550 (E)

Page 48

Revision 2.0

Image 56
Contents NEC America, Inc Liability Disclaimer NEAX2000 IVS Table of Contents List of Figures List of Figures List of Tables This page is for your notes Outline of this Manual Reference ManualsChapter System Description System OutlinePIM PIM ConfigurationPIM Configuration System Configuration 2shows the system configurationRequired Equipment Required EquipmentSN1308 PIM P-A PIM Q-UA SN1420 PIMAB-ARMT PCM-0.3 CA System Capacity System CapacityDaia DAIA, 2 DaicSystem Conditions Time Slot Allocation Time Slot AllocationFor the switch settings This page is for your notes Installation Precaution in HandlingStatic Electricity Guard PBX Installation Procedure StartSee Section See .2.6 See Section Location of Lamps, Switches, and Connectors see Figure Lamp Indications on PN-DAIA Card Switch Settings on PN-DAIA Card Setting of control signal time slot OFFNeutral grounding on the receiving line is not Mounting of Daia Card Mounting Location of Daia Card ND-46550 ESwitch Setting of Daic Card PN-DAIC CardDown Switch Settings on PN-DAIC CardLamp Indications on PN-DAIC Card SW2 Dip SW When mounting this card on remote Mounting of Daic Card Mounting Location of Daic Card Main SiteBUS Cable Connection BUS-DAIA Cable Connection ND-46550 E10 DAIA-DAIC Cable Connection 11 DAIA-DAIC Cable Connection ND-46550 Echapter Revision 12 DAIA-DAIC Cable Connection 13 DAIA-DAIC Cable Connection ND-46550 E 14 PN-DAIB Card Lamp Indications on PN-DAIB Card Switch Settings on PN-DAIB Card TS6 OFF TS7 Down Mounting of Daib Card 15 Mounting Location of Daib Card ND-46550 E16 Mounting Location of Daib Card Refer to , Section 18 Mounting Location of Daic Card Remote PIM 19 Mounting Location of Daic Card Remote PIM ND-46550 E 20 DAIB-DAIC Cable Connection LTC Connector Accommodation Small Platform Mounting of Line/Trunk Card on Small Platform PIMLTC0 LTC122 Location of Each LEN Small Platform LTC0 LTC Connector Accommodation 1000 IVS Mounting of Line/Trunk Card on 1000 IVS PIM25 Location of Each LEN 1000 IVS ND-46550 E 26 LTC Connector Pin Arrangement 1000 IVS PIM N-UB LTC1 10 LTC Connector AccommodationMounting of Line/Trunk Card on PIM N UB 64 port PIM 28 Location of Each LEN PIM NUB LTC0 Power Failure Transfer PFT 30shows an outline of a PFT PN-AUCA connection31 MDF Cross Connection for PFT PN-AUCA ND-46550 E 32shows an outline of a PFT PZ-8PFTA connection PFT0 Connector 34 Mounting PZ-8PFTA Card to PIM 35 PFT Connector Pin Assignment ND-46550 E 36 MDF Cross Connection for PFT PZ-8PFTA PFT1 Connector To Station to PN-4LC to C.O. Line to PN-4COT 37 DTI Cable Connection via LTC Connector PIM0 Daia AA0 BA0 AA1 BA1 LTC1 MDF 39 DTI Cable Connection via CN Connector Main Site DTI Connection at Remote Site MP Reset Daib Remedial Action on Each Lamp StatusPN-DAIA Daia PN-DAIB Daib PN-DAIC Daic This page is for your notes