Emerson UPS Systems installation manual Single-Module Mechanical Installation

Page 10

Single-Module Mechanical Installation

Once the equipment has been finally positioned and secured, connect the power cables as described in the following procedure.

Refer to the appropriate cable connection drawing in 2.0 - Installation Drawings.

1.Verify that the bypass equipment is isolated from its external power source and all the power isolators are open. Check that these supplies are electrically isolated and post any necessary warning signs to prevent their inadvertent operation.

2.Open the door to the cabinet and remove the interior panels.

3.Connect the ground and any necessary main bonding jumper to the equipment ground busbar.

NOTE

The grounding and neutral bonding arrangement must be in accordance with local and national codes of practice.

NOTE

Care must be taken when routing power cable. Ensure that cables do not touch other busbars (see Figure 11).

NOTE

Do not double-stack lugs: do not layer two lugs on the same side of the busbar (see Figure 11).

4.Connect the AC input supply cables between the power distribution panel and the bypass input supply busbars (A-B-C or A-B-C-N terminals) and tighten the connections to the proper torque. Ensure correct phase rotation!

5.If system is one- or two-input, connect the AC input supply cables between the maintenance bypass cabinet and the UPS bypass input supply busbars (A-B-C or A-B-C-N terminals) and tighten the connections to the proper torque.

Ensure correct phase rotation!

6.If system is single-input, connect AC jumper connectors between UPS bypass input supply busbars and UPS rectifier input supply busbars (A-B-C terminals) and tighten the connections to the proper torque.

Ensure correct phase rotation!

7.Connect the system output power cables between the Maintenance Bypass Cabinet output (A-B-C or A-B-C-N terminals) and the critical load and tighten the connections to the proper torque. Ensure correct phase rotation!

8.Connect the auxiliary cables of any external interface/signals to the respective connections of the output auxiliary terminal block (X4) (see2.0 - Installation Drawings).

9.Replace interior panels and close door.

6

Image 10
Contents Liebert NXL Maintenance Bypass Cabinet Product Warranty Registration Table of Contents Figures Important Safety Instructions Introduction Positioning Power Cables Power Cable Connection Procedure Single-Module Mechanical Installation Installation Drawings Two-Breaker Maintenance Bypass Cabinet, two-input, attached Busbar Detail B Front Section A-A Bottom View Footprint Bottom View Footprint TOP View BUS BAR Detail a BUS Termination Detail Cable routing Front Run From Conductor Bypass Installation Drawings P1 D T Installation Drawings Control wiring connections without InterlockControl wiring connections with interlock From PurposeSection A-A Cabinet-to-Cabinet Specifications Liebert NXL Maintenance Bypass Cabinet specificationsRecommended conduit and cable sizes-Maintenance Bypass Input Recommended conduit and cable sizes-Load Output Recommended conduit and cable sizes-Module Bypass InputRecommended conduit and cable sizes-Module Output Recommended conduit and cable sizes-Load Bank OutputRecommended lug sizes #4/0 AWGSpecifications Page Ti n Ne tIti That