Cisco Systems N3KC3524P10G manual Required Tools and Equipment

Page 51

Chapter 2 Installing the Cisco Nexus 3000 Series Switches

Grounding the Switch

Se n d d o c u m e n t c o m m e n t s t o n ex u s 3 k - d o c f e e d b a ck @ c i sc o . c o m

Required Tools and Equipment

To connect the system ground, you need the following tools and materials:

Grounding lug—A two-hole standard barrel lug. This lug supports up to 6 AWG wire. This lug is supplied in the accessory kit.

Grounding screws—Two M4 x 8mm (metric) pan-head screws. These screws are supplied as part of the accessory kit.

Grounding wire—Not supplied in the accessory kit. The grounding wire should be sized according to local and national installation requirements. Depending on the power supply and system, a 12 AWG to 6 AWG copper conductor is required for U.S. installations. Commercially available 6 AWG wire is recommended. The length of the grounding wire depends on the proximity of the switch to proper grounding facilities.

No. 1 Phillips screwdriver.

Crimping tool to crimp the grounding wire to the grounding lug.

Wire-stripping tool to remove the insulation from the grounding wire.

Grounding the Cisco Nexus 3000 Series Chassis

The chassis has a grounding pad with two threaded M4 holes for attaching a grounding lug. The system ground is located on the left side of the chassis (left of the front) on the Cisco Nexus 3000 Series switches.

Warning When installing or replacing the unit, the ground connection must always be made first and disconnected last. Statement 1046

Caution We recommend grounding the chassis, even if the rack is already grounded.

Caution All power supplies must be grounded. The receptacles of the AC power cables used to provide power to the chassis must be the grounding type, and the grounding conductors should connect to protective earth ground at the service equipment.

Warning When installing or replacing the unit, the ground connection must always be made first and disconnected last.

Statement 1046

To attach the grounding lug and cable to the chassis, follow these steps:

Step 1 Use a wire-stripping tool to remove approximately 0.75 inches (19 mm) of the covering from the end of the grounding cable.

Step 2 Insert the stripped end of the grounding cable into the open end of the grounding lug (see Callout 1 in Figure 2-6).

 

 

Cisco Nexus 3000 Series Hardware Installation Guide

 

 

 

 

 

 

OL-25338-04

 

 

2-13

 

 

 

 

 

Image 51
Contents Americas Headquarters Cisco Nexus 3000 Series Hardware Installation GuidePage N T E N T S Airflow Direction Chassis Weight Chassis and Module Information E-4 Contents Audience OrganizationChapter and Title Description Bewaar Deze Instructies ConventionsGuarde Estas Instruções Spara Dessa Anvisningar GEM Disse Anvisninger Xii Related Documentation Error and System Messages Configuration GuidesInstallation and Upgrade Guides Command ReferencesObtaining Documentation and Submitting a Service Request Xvi Airflow Direction Layer 3 License Part Number Cisco Nexus 3016 SwitchFront View of the Cisco Nexus 3016 Switch Chassis for the Cisco Nexus 3016 SwitchID LED Ports for the Cisco Nexus 3016 SwitchAirflow Direction Power Supply Part Number Power Supply for the Cisco Nexus 3016 SwitchFan Tray for the Cisco Nexus 3016 Switch Port Connections for the Cisco Nexus 3016 SwitchPart Number Transceivers and Cables Cisco Nexus 3048 Switch Chassis for the Cisco Nexus 3048 SwitchPower Supply Airflow Direction Layer 3 License Part Number Front View of the Cisco Nexus 3048 Switch Rear View of the Cisco Nexus 3048 Switch Ports for the Cisco Nexus 3048 SwitchPower Supply for the Cisco Nexus 3048 Switch Port Connections for the Cisco Nexus 3048 Switch Fan Tray for the Cisco Nexus 3048 SwitchCisco Nexus 3064 Switch Front View of the Cisco Nexus 3064 Switch Chassis for the Cisco Nexus 3064 SwitchRear View of the Cisco Nexus 3064 Switch Ports for the Cisco Nexus 3064 SwitchFan Tray for the Cisco Nexus 3064 Switch Power Supply for the Cisco Nexus 3064 SwitchPort Connections for the Cisco Nexus 3064 Switch Chassis for the Cisco Nexus 3548 Switch Cisco Nexus 3548 SwitchPower Supplies Fan tray Rear View of the Cisco Nexus 3548 Switch Ports for the Cisco Nexus 3548 SwitchFan Tray for the Cisco Nexus 3548 Switch Power Supply for the Cisco Nexus 3548 SwitchPort Connections for the Cisco Nexus 3548 Switch SFP-10G-ER Cisco Nexus 3000 Series Hardware Installation Guide Statement Preparing for Installation Installation Options with Racks and CabinetsAirflow Direction Installation Guidelines Chassis WeightCisco Nexus 3000 Series Hardware Installation Guide Unpacking and Inspecting the Switch Installing the SwitchChassis Quantity Part DescriptionStep Installing the Slider Rails Sliding the Chassis Into the Rack Electrostatic Discharge Damage, page·2-14 Grounding the SwitchEnvironment Severity Level Grounding Recommendations Proper Grounding PracticesEstablishing the System Ground Grounding the Cisco Nexus 3000 Series Chassis Required Tools and EquipmentGrounding a Cisco Nexus 3000 Series Chassis Preventing Electrostatic Discharge DamageOL-25338-04 Attaching the ESD Wrist Strap to the System Ground Lug Screw Starting the Switch 331410 OL-25338-04 Cisco Nexus 3000 Series Hardware Installation Guide Connecting to the Network Preparing for Network Connections Connecting to the Console PortConnecting to a Server Connecting to the Management PortInstalling an SFP or SFP+ Transceiver Installing and Replacing SFP or SFP+ TransceiversReplacing an SFP or SFP+ Transceiver Installing Optical Cables into SFP or SFP+ TransceiversInstalling an Optical Cable into an SFP or SFP+ Transceiver Maintaining SFP and SFP+ Transceivers and Fiber-Optic Cables Cisco Nexus 3000 Series Hardware Installation Guide Removing an AC Power Supply Replacing a Power SupplyInstalling an AC Power Supply Removing a DC Power Supply Replacing a Fan Tray Installing a DC Power SupplyRemoving a Fan Tray Removing a Fan Tray, Installing a Fan Tray,Installing a Fan Tray General Requirements for Cabinets and Racks Cabinet and Rack RequirementsRequirements Specific to Standard Open Racks Requirements Specific to Perforated CabinetsCable Management Guidelines Cisco Nexus 3000 Series Hardware Installation Guide Switch Specifications Environmental SpecificationsSwitch Height Width Depth Weight Power Specifications Property Cisco Nexus 3000 Series SwitchProperty AC Power Supply N2200-PAC-400 W Property AC Power Supply N2200-PAC-400 W Appendix B Technical Specifications Power Specifications Console Cable Cable and Connector SpecificationsDescription Feet Meters Illustration Supported Power Cords and PlugsConsole Port LengthCAB-N5K6A-NA CAB-9K10A-AU Figure C-6 SFS-250V-10A-ID CAB-9K10A-SW CAB-N5K6A-NA Figure C-15 Jumper Power CordLED Descriptions Chassis and Module LED Descriptions ComponentStatus Description Fail LED Status Amber Power Supply StatusPort LEDs ConditionRight Off No activity Blinking green Activity Site Preparation Checklist Site Planning and Maintenance RecordsTask No Planning Activity Verified By Time Date Contact and Site Information Chassis and Module Information D E IN-2 IN-3 IN-4 IN-5 IN-6