Cisco Systems N3KC3524P10G manual Installing and Replacing SFP or SFP+ Transceivers

Page 62

Chapter 3 Connecting to the Network

Connecting to a Server

Se n d d o c u m e n t c o m m e n t s t o n ex u s 3 k - d o c f e e d b a ck @ c i sc o . c o m

shorter copper cables, which can connect to another 40-Gigabit QSFP+ port or four 10-Gigabit SFP+ ports. If the servers or switches are further than 16.4 feet (5 meters), it is best to use the optical cable that has 40-Gigabit transceivers on both ends.

For the Cisco Nexus 3048 switch, you must use RJ-45 connectors on copper cables to make the 10/100/1000 Ethernet downlink connections, and you must use SFP transceivers on copper or optical cables or SFP+ transceivers on optical cables to make the 1- or 10-Gigabit Ethernet uplink connections.

For the Cisco Nexus 3064 switch, you must use RJ-45 connectors on copper cables to make the downlink connections and SFP transceivers on copper or optical cables or SFP+ transceivers on optical cables to make the 1- or 10-Gigabit Ethernet uplink connections.

This section includes the following topics:

Installing and Replacing SFP or SFP+ Transceivers, page 3-4

Installing Optical Cables into SFP or SFP+ Transceivers, page 3-5

Installing and Replacing SFP or SFP+ Transceivers

Caution Excessively removing and installing an SFP or SFP+ transceiver can shorten its life. Unless it is absolutely necessary, do not remove and insert SFP or SFP+ transceivers. To prevent damage to an optical cable and transceiver, we recommend that you disconnect cables before installing or removing transceivers.

This section includes the following topics:

Installing an SFP or SFP+ Transceiver, page 3-4

Replacing an SFP or SFP+ Transceiver, page 3-5

Installing an SFP or SFP+ Transceiver

To install an SFP or SFP+ transceiver, follow these steps:

Step 1 Attach an ESD-preventive wrist strap and follow its instructions for use.

Step 2 Remove the dust cover from the port cage.

Step 3 Remove the dust cover from the port end of the transceiver.

Step 4 Insert the transceiver into the port as follows:

If the transceiver has a Mylar tab latch, position the transceiver with the tab on the bottom, and then gently insert the transceiver into the port until it clicks into place.

If the transceiver has a bale clasp latch, position the transceiver with the clasp on the bottom, close the clasp by pushing it up over the transceiver, and then gently insert the transceiver into the port until it clicks into place.

Caution If the transceiver does not install easily, ensure that it is correctly positioned and the tab or clasp are in the correct position before continuing.

Cisco Nexus 3000 Series Hardware Installation Guide

3-4

OL-25338-04

 

 

Image 62
Contents Cisco Nexus 3000 Series Hardware Installation Guide Americas HeadquartersPage N T E N T S Airflow Direction Chassis Weight Chassis and Module Information E-4 Contents Chapter and Title Description AudienceOrganization Conventions Bewaar Deze InstructiesGuarde Estas Instruções Spara Dessa Anvisningar GEM Disse Anvisninger Xii Related Documentation Command References Configuration GuidesInstallation and Upgrade Guides Error and System MessagesObtaining Documentation and Submitting a Service Request Xvi Cisco Nexus 3016 Switch Airflow Direction Layer 3 License Part NumberChassis for the Cisco Nexus 3016 Switch Front View of the Cisco Nexus 3016 SwitchPorts for the Cisco Nexus 3016 Switch ID LEDPower Supply for the Cisco Nexus 3016 Switch Airflow Direction Power Supply Part NumberPart Number Transceivers and Cables Fan Tray for the Cisco Nexus 3016 SwitchPort Connections for the Cisco Nexus 3016 Switch Power Supply Airflow Direction Layer 3 License Part Number Cisco Nexus 3048 SwitchChassis for the Cisco Nexus 3048 Switch Front View of the Cisco Nexus 3048 Switch Ports for the Cisco Nexus 3048 Switch Rear View of the Cisco Nexus 3048 SwitchPower Supply for the Cisco Nexus 3048 Switch Fan Tray for the Cisco Nexus 3048 Switch Port Connections for the Cisco Nexus 3048 SwitchCisco Nexus 3064 Switch Chassis for the Cisco Nexus 3064 Switch Front View of the Cisco Nexus 3064 SwitchPorts for the Cisco Nexus 3064 Switch Rear View of the Cisco Nexus 3064 SwitchPower Supply for the Cisco Nexus 3064 Switch Fan Tray for the Cisco Nexus 3064 SwitchPort Connections for the Cisco Nexus 3064 Switch Cisco Nexus 3548 Switch Chassis for the Cisco Nexus 3548 SwitchPower Supplies Fan tray Ports for the Cisco Nexus 3548 Switch Rear View of the Cisco Nexus 3548 SwitchPower Supply for the Cisco Nexus 3548 Switch Fan Tray for the Cisco Nexus 3548 SwitchPort Connections for the Cisco Nexus 3548 Switch SFP-10G-ER Cisco Nexus 3000 Series Hardware Installation Guide Statement Airflow Direction Preparing for InstallationInstallation Options with Racks and Cabinets Chassis Weight Installation GuidelinesCisco Nexus 3000 Series Hardware Installation Guide Installing the Switch Unpacking and Inspecting the SwitchQuantity Part Description ChassisStep Installing the Slider Rails Sliding the Chassis Into the Rack Grounding the Switch Electrostatic Discharge Damage, page·2-14Proper Grounding Practices Environment Severity Level Grounding RecommendationsEstablishing the System Ground Required Tools and Equipment Grounding the Cisco Nexus 3000 Series ChassisPreventing Electrostatic Discharge Damage Grounding a Cisco Nexus 3000 Series ChassisOL-25338-04 Attaching the ESD Wrist Strap to the System Ground Lug Screw Starting the Switch 331410 OL-25338-04 Cisco Nexus 3000 Series Hardware Installation Guide Connecting to the Network Connecting to the Console Port Preparing for Network ConnectionsConnecting to the Management Port Connecting to a ServerInstalling and Replacing SFP or SFP+ Transceivers Installing an SFP or SFP+ TransceiverInstalling Optical Cables into SFP or SFP+ Transceivers Replacing an SFP or SFP+ TransceiverInstalling an Optical Cable into an SFP or SFP+ Transceiver Maintaining SFP and SFP+ Transceivers and Fiber-Optic Cables Cisco Nexus 3000 Series Hardware Installation Guide Replacing a Power Supply Removing an AC Power SupplyInstalling an AC Power Supply Removing a DC Power Supply Installing a DC Power Supply Replacing a Fan TrayRemoving a Fan Tray, Installing a Fan Tray, Removing a Fan TrayInstalling a Fan Tray Cabinet and Rack Requirements General Requirements for Cabinets and RacksRequirements Specific to Perforated Cabinets Requirements Specific to Standard Open RacksCable Management Guidelines Cisco Nexus 3000 Series Hardware Installation Guide Switch Height Width Depth Weight Switch SpecificationsEnvironmental Specifications Property AC Power Supply N2200-PAC-400 W Power SpecificationsProperty Cisco Nexus 3000 Series Switch Property AC Power Supply N2200-PAC-400 W Appendix B Technical Specifications Power Specifications Cable and Connector Specifications Console CableLength Supported Power Cords and PlugsConsole Port Description Feet Meters IllustrationCAB-N5K6A-NA CAB-9K10A-AU Figure C-6 SFS-250V-10A-ID CAB-9K10A-SW CAB-N5K6A-NA Jumper Power Cord Figure C-15LED Descriptions Status Description Chassis and Module LED DescriptionsComponent Condition Power Supply StatusPort LEDs Fail LED Status AmberRight Off No activity Blinking green Activity Site Planning and Maintenance Records Site Preparation ChecklistTask No Planning Activity Verified By Time Date Contact and Site Information Chassis and Module Information D E IN-2 IN-3 IN-4 IN-5 IN-6