Chapter 3 Power Supply Installation
Figure 3-4 Crimping the Terminal Lug
280938
Step 4 Slide the ground screw from Step 1 through the terminal lug. Insert the ground screws into the opening on the cable side.
Figure 3-5 Attaching the Terminal Lug
208335
1
Step 5 Use a ratcheting torque screwdriver to tighten the ground screws to 30
Step 6 Attach the other end of the ground wire to a grounded bare metal surface, such as a ground bus or a grounded bare rack.
Installing the Power-Supply Module in the Switch
Step 1 We recommend that power be off at the AC or DC circuits. Locate the circuit breakers, turn them OFF, and tape them in the OFF position.
Note If the power is not off at the AC or DC circuit breaker, do not touch the
Step 2 Use a Phillips screwdriver to loosen the two captive screws of the blank
Cisco IE 3010 Switch Hardware Installation Guide
| ||
|