4. Test Procedures

4.1 Overview

This chapter gives you several suggested test procedures. However, it is by no means the only way to use the Test Set to isolate trouble or to verify lines.

NOTE: The following procedures assume certain conditions exist (that procedures are followed in the correct order.) These conditions are described at the beginning of each procedure.

TEST CONFIGURATIONS

Test Configuration 1 — Point-to-Point — NT1 (Figure 4-1)

To put the circuit in the point-to-point test configuration:

1. Disconnect the terminal.

NOTE: With a passive bus, testing the S/T interface may disrupt the operation of other devices on the bus.

2.Connect the jack to either Port A or Port B of the Test Set.

3.The Test Set should be terminated; the TERMINATE button should be out.

BRTS-100 UNIT

 

NT1

 

 

 

 

 

 

 

POINT TO POINT — NT1

Figure 4-1. Test Configuration 1.

14

Image 15
Contents BRTS-100 Isdn Test Set FCC Statement BRTS-100 Isdn Test SET NOM Statement Trademarks Used in this Manual Contents Specifications How to Use This Manual IntroductionOverview 100 Est FeaturesOperation Connecting the UnitBRTS-100 Isdn Test Set controls and indicators Passive BUS Powering Up the Unit Controls and Indicators Feature ButtonsIndicators Test Status PASS/FAIL Lights Reflects test status Modes of OperationTest Configuration 1 Point-to-Point NT1 Figure Test ProceduresTest Procedures Comprehensive Troubleshooting Procedure Comprehensive troubleshooting flow chart 1 Comprehensive troubleshooting flow chart 2 Phantom Conclusion Light Check PowerCheck Loop Check PowerTest Procedures Check loop flow chart 1 Check loop flow chart 2 Check loop flow chart 3 Test Procedures Passive Bus-Check Terminations Passive Bus Configuration Check TerminationsTest Procedures Proper device terminations diagram Pair Reversal Pair reversal flow chart 1 Pair reversal flow chart 2 10. Pair reversal diagram Monitor 11. Monitor flow chart Technical Reference Power-Source IndicatorsActivation/Deactivation Modes Activation/deactivation procedureLine Test/Transmit See Figure Receive TestLevel Test Transmit and line test DC Continuity AC ImpedanceAC impedance Two Test Set units used for tracing SpeakerBattery Replacement Appendix MaintenanceFigure A-2. Replacing the 8-Pin Jack Connectors Pin Jack ReplacementCopyright 2002. Black Box Corporation. All rights reserved