10.Put the Test Set in the CONTINUITY Test Mode.

11.a. If the Green Test Status light goes on, there is a physical connection between the terminal and the NT1.

b.If the Red Test Status light goes on, there is no continuity on the receive pair between the terminal and the NT1. You should check the loop for opens. There’s no need for any further testing.

12.The problem may be that the signal received at the NT1 is too low.

To check this, put the Test Set back in the NORMAL mode by pushing the LINE button.

13.Put the Test Set in the LEVEL test mode.

14.a. If the Green Test Status light goes on, the terminal is receiving the proper level. The problem may be that either the switch or the NT1 isn’t working.

b.If the Red Test Status light goes on, the signal level at the terminal is too low. Check the loop length.

25

Image 26
Contents BRTS-100 Isdn Test Set FCC Statement BRTS-100 Isdn Test SET NOM Statement Trademarks Used in this Manual Contents Specifications Overview How to Use This ManualIntroduction Features 100 EstConnecting the Unit OperationBRTS-100 Isdn Test Set controls and indicators Passive BUS Indicators Powering Up the UnitControls and Indicators Feature Buttons Modes of Operation Test Status PASS/FAIL Lights Reflects test statusTest Procedures Test Configuration 1 Point-to-Point NT1 FigureTest Procedures Comprehensive Troubleshooting Procedure Comprehensive troubleshooting flow chart 1 Comprehensive troubleshooting flow chart 2 Check Power Phantom Conclusion LightCheck Power Check LoopTest Procedures Check loop flow chart 1 Check loop flow chart 2 Check loop flow chart 3 Test Procedures Passive Bus Configuration Check Terminations Passive Bus-Check TerminationsTest Procedures Proper device terminations diagram Pair Reversal Pair reversal flow chart 1 Pair reversal flow chart 2 10. Pair reversal diagram Monitor 11. Monitor flow chart Power-Source Indicators Technical ReferenceActivation/deactivation procedure Activation/Deactivation ModesLevel Test Line Test/Transmit See FigureReceive Test Transmit and line test AC Impedance DC ContinuityAC impedance Speaker Two Test Set units used for tracingAppendix Maintenance Battery ReplacementPin Jack Replacement Figure A-2. Replacing the 8-Pin Jack ConnectorsCopyright 2002. Black Box Corporation. All rights reserved