CHAPTER 4: Test Procedures

4.7 Monitor

Use this test when you’ve determined there’s nothing physically wrong with the circuit. The MONITOR procedure checks for any D channel activity. See the Monitor Flow Chart in Figure 4-11 for an outline of the functions performed during this test.

Before using this procedure, the following prerequisites must be met:

1.All terminals are properly terminated (CHECK TERMINATIONS).

2.No pair reversals exist on a passive bus (PAIR REVERSAL).

3.LINE TEST passes.

4.Terminal does not work properly.

5.Terminal receiving proper power (CHECK POWER).

If all prerequisites exist, proceed with the MONITOR test procedure.

1.Put the Test Set in UNTERMINATED and NORMAL modes.

2.Put circuit in Test Configuration 2.

3.Put the Test Set in the D Activity test mode.

4.Press the INITIATE button.

5.Try to initiate a call with the terminal.

6.a. If the Red Test Status light flashes, the terminal is putting D channel data on the bus. There’s a problem with the switch. Possibly the switch parameters are set wrong.

b. If the Red Test Status light does not flash, the terminal is not outputting any D channel data. Check your terminal.

This section gives you the Test Set’s circuit-level information.

33

Image 34
Contents BRTS-100 Isdn Test Set FCC Statement BRTS-100 Isdn Test SET NOM Statement Trademarks Used in this Manual Contents Specifications Introduction How to Use This ManualOverview Features 100 EstConnecting the Unit OperationBRTS-100 Isdn Test Set controls and indicators Passive BUS Controls and Indicators Feature Buttons Powering Up the UnitIndicators Modes of Operation Test Status PASS/FAIL Lights Reflects test statusTest Procedures Test Configuration 1 Point-to-Point NT1 FigureTest Procedures Comprehensive Troubleshooting Procedure Comprehensive troubleshooting flow chart 1 Comprehensive troubleshooting flow chart 2 Check Power Phantom Conclusion LightCheck Power Check LoopTest Procedures Check loop flow chart 1 Check loop flow chart 2 Check loop flow chart 3 Test Procedures Passive Bus Configuration Check Terminations Passive Bus-Check TerminationsTest Procedures Proper device terminations diagram Pair Reversal Pair reversal flow chart 1 Pair reversal flow chart 2 10. Pair reversal diagram Monitor 11. Monitor flow chart Power-Source Indicators Technical ReferenceActivation/deactivation procedure Activation/Deactivation ModesReceive Test Line Test/Transmit See FigureLevel Test Transmit and line test AC Impedance DC ContinuityAC impedance Speaker Two Test Set units used for tracingAppendix Maintenance Battery ReplacementPin Jack Replacement Figure A-2. Replacing the 8-Pin Jack ConnectorsCopyright 2002. Black Box Corporation. All rights reserved