CHAPTER 4: Test Procedures

1.Determine which devices are the first and last devices on the bus. The first device is the one closest to the NT1. The last device is the one furthest from the NT1. See Figure 4-8for an example of proper device termination.

2.Go to the first device on the bus.

3.Put the Test Set in TERMINATED and NORMAL mode.

4.Put circuit in Test Configuration 3.

5.Make sure the Test Set is in REVerse mode; LINE button should be in.

6.Power down the terminal.

7.Put the Test Set in the IMPEDANCE test mode.

8.a. If the Green Test Status light goes on, the terminal is terminated. Unterminate the terminal by following the instructions in the terminal’s user manual.

b.If the Rest Test Status light goes on, no change in the termination is necessary.

9.Go to the next device on the bus. If the terminal is NOT the last device on the bus, go to step four. Otherwise, continue on to step 10.

10.You should be at the last device on the bus. Repeat steps four through seven.

11.a. If the Green Test Status light goes on, the terminal is properly terminated.

b.If the Red Test Status light goes on, the terminal is not terminated. Terminate the terminal by following the instructions in the terminal’s

user guide.

All devices on the bus should now be properly terminated.

27

Image 28
Contents BRTS-100 Isdn Test Set FCC Statement BRTS-100 Isdn Test SET NOM Statement Trademarks Used in this Manual Contents Specifications Introduction How to Use This ManualOverview Features 100 EstConnecting the Unit OperationBRTS-100 Isdn Test Set controls and indicators Passive BUS Controls and Indicators Feature Buttons Powering Up the UnitIndicators Modes of Operation Test Status PASS/FAIL Lights Reflects test statusTest Procedures Test Configuration 1 Point-to-Point NT1 FigureTest Procedures Comprehensive Troubleshooting Procedure Comprehensive troubleshooting flow chart 1 Comprehensive troubleshooting flow chart 2 Check Power Phantom Conclusion LightCheck Power Check LoopTest Procedures Check loop flow chart 1 Check loop flow chart 2 Check loop flow chart 3 Test Procedures Passive Bus Configuration Check Terminations Passive Bus-Check TerminationsTest Procedures Proper device terminations diagram Pair Reversal Pair reversal flow chart 1 Pair reversal flow chart 2 10. Pair reversal diagram Monitor 11. Monitor flow chart Power-Source Indicators Technical ReferenceActivation/deactivation procedure Activation/Deactivation ModesReceive Test Line Test/Transmit See FigureLevel Test Transmit and line test AC Impedance DC ContinuityAC impedance Speaker Two Test Set units used for tracingAppendix Maintenance Battery ReplacementPin Jack Replacement Figure A-2. Replacing the 8-Pin Jack ConnectorsCopyright 2002. Black Box Corporation. All rights reserved